Norochcholai Phase II:
More power for national grid soon
By Gamini Warushamana
Construction work on buildings and installing of generators in the
second phase of the Lakwijaya coal power plant in Norochcholai has been
completed and a test run of the plant was done recently, said Ceylon
Electricity Board (CEB), General Manager Shavindranath Fernando.
With the completion of Phase II which has a capacity of 2 x 300 MW,
the total capacity of the Norochcholai power plant has increased to 900
MW. The project was due to be completed by May this year.
Fernando said that the construction work in the second phase was done
carefully taking into account the problems encountered in Phase I.
“We had to ensure every step was perfectly completed and therefore,
it took time.
During the test runs there were no major problems. We can't give an
exact date for the commissioning of the plant but it will be soon,”
Fernando said.
Phase I of the project with a capacity of 300 MW was commissioned in
March 2010.
The frequent breakdown of generators from the day of commissioning
sparked serious criticism over the Chinese technology used in the
project.
Investment in Phase-I of the project was US $450 million and
investment in phase-II is US $891 million. The project has been funded
by a soft loan from Exim Bank of China.
Fernando said that issues related to the transmission line across the
Puttalam lagoon will be sorted out and there is a progress in the
discussions with fishery societies.
Analysts said that completion of the project and the addition of 600
MW to the national grid will ease CEB's burden of high cost thermal
power generation. The weighted average generation cost is expected to
decline with the addition of the 600 MW.
CEB sources said that generation cost per unit has increased
significantly this year as a result of declined hydro capacity due to
the prevailing drought.
The weighted average generation cost per unit increased to Rs. 24.37
compared to Rs. 17.70 in 2013.
However, the Lakvijaya coal power plant has reduced the burden of the
CEB by contributing 18.9 percent of the generation mix according to the
latest statistics of the CEB. If 300 MW from coal power was not
available the unit cost would have been much higher, analysts said. |