Port City: Govt and Chinese investor settle issues:
Flagship development project gets off the ground
by Ranil Wijayapala
After many months of scrutiny on the US$ 1.4 billion Colombo Port
City project, the single largest foreign direct investment project in
the island is to get off the ground in the coming weeks, after the Sri
Lankan Government and the Chinese investor amicably settling some thorny
issues, following the conditional environmental clearance issued on
March 8.
The government is now in the process of re-negotiating the terms and
conditions of the Concession Agreement which is to be signed between the
Government and the Chinese investor soon, stipulating the services and
benefits shared between the Government of Sri Lanka and the investor
through the implementation of the project.
"At present there is no barrier for the Chinese investor to restart
the project as the necessary clearance has already been given by the
government for the project to go ahead", Secretary to the Megapolis and
Western Development Ministry, Nihal Rupasinghe told the Sunday Observer.
The Urban Development Authority under the Ministry of Megapolis and
Western Development is now coordinating the Colombo Port City project as
a part of the Megapolis development plan, the flagship development
project of the government.
As a part of these on-going negotiations on the Concession Agreement,
the Government is also negotiating with the investor on the 125 million
US dollars claimed by the investor as compensation for suspending the
project for nearly one year.
The matter, however, was due to be raised during Prime Minister Ranil
Wickremesinghe's visit to China last week as the Government claimed that
it was not in a position to pay such compensation to the Chinese
investor for the suspension of the project for nearly one year
"Therefore, the Government is hoping to arrive at a conclusion over
the Concession Agreement that is to be signed probably in May between
the Government and the Chinese investor based on the outcome of the
on-going negotiations and also based on the Premier's discussions with
the Chinese government during his visit to China", Rupasinghe added.
However, he pointed out that the Government is in a strong position
to negotiate over the 125 million US dollar claim by the Chinese
investor, based on the argument that it has not taken the requisite
approval for the project to go ahead without any interruption by the
Government.
The Coast Conservation and Coastal Resource Management Department on
March 8, 2016 gave its conditional approval for the project based on the
Supplementary Environmental Impact Assessment Report by the Megapolis
and Western Development Ministry. The new project proponent on behalf of
the Colombo Port City project stipulates 72 conditions to be adhered to
when the projec is implemented..
On lease basis
Apart from the US dollar 125 million compensation issue, the
Government has also negotiated quite a number of other issues with the
Chinese investor, and they have already come to an agreement with the
Government over the use of lands on lease basis, deviating from the
earlier agreement of giving them the ownership of the reclaimed lands as
an outright grant.
"The Chinese investor has also agreed to handle the reclaimed lands
under the project through a joint committee comprising the Sri Lanka
government and the representatives of the Chinese investor", the senior
official added.
The Concession Agreement will also focus on the the supply of
electricity and water for the project and several other issues that were
raised when the project was under review.
"The negotiations over these issues are expected to be completed by
the end of this month based on the outcome of Prime Minister Ranil
Wickremsinghes's visit to China and the Concession Agreement is expected
to be signed in May with the Chinese investor overcoming all the hurdles
prior to the project getting off the ground", he added.
Meanwhile, some experts who closely followed up the progress of the
project told the Sunday Observer on the condition of anonymity, the
project has become a factor of salvaging Sri Lanka's economy from the
present stagnation and crisis situation, rekindling Chinese funding back
to the country.
"Therefore, we are more of the view that the government renegotiates
the agreement and it should not become a project which would hamper the
future infrastructure development projects in the country or that could
thrust a huge economic burden on the country".
"Those negotiations should make sure that the project would attract
further foreign direct investments to the country which can give the due
share of benefits to the country, considering the enormous resources and
commitments the Government has to make for this project to be a success.
The experts, therefore, say that Sri Lanka should not disregard or
underestimate the resources it commits, such as sea extent, sand and
quarry material and other resources required for the Colombo Port City
project when negotiating and sharing the benefits of the project.
"The huge investment Sri Lanka should commit on the project in
providing electricity, water and for waste management has to be taken
seriously when sharing the benefits of the projects.Else, this will
become a huge burden to the country", they added.
According to Director General of the Coast Conservation and Coastal
Resources Management Department, Prabhath Chandrakeerthi, the project
approving agency, they have laid down strict conditions when issuing
permits for the reclamation of the sea bed area to form 269 hectares of
land within the total project area of 446.61 hectares.
Breakwater
In the earlier Environment Impact Assessment report which was done by
the Sri Lanka Ports Authority, approval was given only for the
reclamation 232 hectares of land area.
"In the previous EIA, they had not covered beyond the reclamation
area and they have not included the breakwater. In this report they have
covered the entire project area including the breakwater", he added.
"Accordingly, approval was granted for the entire project area and
dredging of the 65 million cubic meters of sea sand, construction of
offshore breakwaters, edge revetments/sea walls, submerged groynes,
inner breakwater, sand barriers, marina basin, lagoon, canal artificial
beaches and other coastal protection structures, supply of approximately
3.45 million cubic meters of rock material for marine structures and to
construct groynes on the southern side of the Beira Lake outlet", he
said.
According to Chandrakeerthi, approval has been granted only for the
reclamation of the sea bed and dredging for sand mining. For the
construction they need to submit a separate EIA as those aspects are not
covered in this EIA report.
"They have not given any idea about the construction they are going
to have in the reclaimed land", he added.
According to Director Coastal Resource Management of the Coast
Conservation and Coastal Resource Management Department,Gamini Hewage,
when granting approval for the project they have laid down a series of
conditions and one key condition is that they should seek approval of
the President for any reclamation of sea.
"According to the Land Ordinance they have to get the authorisation
from the President for dredging the sea bed and reclaiming the sea
bed.Without the authorisation of the President they can't carry out the
reclamation of the sea for the project", he said.
According to the conditions laid down by the CCD, sand extraction can
only be done from the sea area - three kilometers away from the shore
line to minimise the impact on the fishermen and the fishing breeding
ground.
"In the Supplementary EIA, they they have identified two locations
for sand extraction and one location they have identified is a little
bit close to the shoreline. Therefore, we laid down the condition that
they extract sand only from the site one area, that is located three
kilometers away from the shoreline", he added.
This is to ensure that f the ing breeding grounds located within the
three-kilometer boundary will not be disturbed through sand mining..
"During the construction period, they should make the necessary
arrangements for the nourishment of the beach area for fishermen and the
fishing community to land their fishing gear. They have to create an
artificial beach for fishermen putting 300,000 cubic meters of sand for
he nourishment of the northern side of the project area during the
construction period", he said.
Fishing community
"They have to allocate Rs.500 million to the Ministry of Fisheries
not as compensation but to improve the livelihood of the fishing
community in the affected region", he said.
If there is sea erosion or any environmental issue, the project
proponent has agreed to provide solutions for these issues.
With regard to the supply of quarry material for reclamation, they
have to obtain quarry material from the Geological Survey and Mines
Bureau and the Central Environment Authority approved metal quarries in
the country and cannot go for new quarry sites.
According to the SEIA report, the project proponent will use the
northern harbour entrance to enter the project site and use barges to
transport quarry material to the site.
"We had a special committee when granting approval for the project.
In this report, we covered all aspects of the project and the technical
committee appointed by the Coast Conservation Department studied the
report. In the special committee, there were professionals and we
prepared the terms of reference in consultation with them", he added.
"We are monitoring the project throughout the implementation process
and there is a monitoring committee also.They have to submit the
environmental management plan before implementation and this will be the
basis for monitoring during the construction period", Hewage said. |