Environmental regulator raises serious concerns:
PUC grants conditional approval for CEB’s plan
Rukshana Rizwie
While environmental regulator of the power sector have raised serious
concerns over the new inclusions, the Public Utilities Commission of Sri
Lanka (PUCSL) has granted conditional approval for an interim generation
plan submitted by the Ceylon Electricity Board.
The point of contention in the CEB’s interim generation plan is
the inclusion of five new coal power plants, despite strong resistance
from the environmental regulator.
Environmental Foundation (Guarantee) Limited which has already filed
a case in Supreme Court over the proposed coal power plant in Sampur
said they were concerned over the new inclusivity.
“EFL is concerned that at a time when the rest of the world is
phasing out coal power plants, we have not shifted our focus to meet our
immediate and long term energy requirements through renewable sources,”
an official said.
In a letter submitted to the PUCSL on July 27th undersigned by M.C
Wickramasekera, General Manager of the CEB, the board has enlisted five
new coal power plants as part of the Base Case Plan for the year
2017-2036. The CEB notes that the board awaits a policy directive from
the government on whether to proceed with these proposed power plants
which are to be developed in Sampur.
“These power plants are to be developed at Sampur, if permission is
granted by the Government of Sri Lanka. Otherwise new location is to be
found,” the report reads.
However, when the EFL case was taken up in Supreme Court, their
counsel K.Kanglsvaran told courts that they had learnt the government
had taken a policy decision to convert the proposed Coal power plant
into a Liquefied Natural Gas (LNG) plant but wanted an assurance that it
would be done. The next hearing has been fixed for September 5th.
The PUCSL however has directed the CEB to furnish a Long Term
Generation Plan for 2015-2034 or the entire 2017-2036 with sufficient
justification for skipping the 2015 plan by September 1st this year.
In an attempt to overcoming a looming power crisis in the year 2018,
the CEB has also proposed that the 35 megawatt Broadlands and 120
megawatt Uma Oya hydro power plant be in operation by the year 2018.
Thermal additions include five new coal power plants. The report
notes that the coal power plants are to be developed at Sampur, if
permission is granted by the government, otherwise a new location is to
be found for them.
The Base Plan is also anchored by several thermal retirements which
include the 4 x 17 megawatt Kelanitissa Gas Turbines, 4 x 18 megawatt
Sapugaskanda diesel and the 4 x 15 megawatt Barge power plant among
others.
Based on their demand forecast, the CEB predicts that the demand in
GHw would be around 13156 for the year 2017 while the generation would
be 14720 GHw. The annual growth in demand is around 5.0% while
generation will increase by 5.1% next year and 6.1% the year after.
The PUCSL however has observed that the CEB has not considered
several factors including Demand side management, demand forecast,
absorbing more electricity from readily available energy sources, a
transmission system that takes into account cost minimization and most
of all an alternative to the Sampur Power Plant which was reportedly
shelved. |