Imminent energy
shortage:
PUCSL challenges CEB for solution
By Rukshana Rizwie
Energy supply sector regulator, the Public Utilities Commission (PUCSL), this
week revealed that a deepening power crisis in the country was being exacerbated
by sluggish reforms and a lethargic Ceylon Electricity Board.
 |
Energy deficit of 500
megawatts by 2018 |
Damitha Kumarasinghe Director General at PUCSL is warning that even with the
many planned power production plant additions, Sri Lanka would yet have energy
and capacity shortages in the years 2018, 2019 and beyond. “The real challenge
would be to get these plants implemented,” he said. “We are looking at a short
time frame of one and a half years.”
He added that the CEB will need to commission many of the plants listed in the
Least Cost Long Term Generation Expansion Plan (LCLTGEP) 2015- 2034 if the
country was to avert a power crisis in the near future. Within the next four
years, 1,275 megawatts (MW) will need to be added to the national grid.
Based on forecasts by the Ceylon Electricity Board, Sri Lanka’s electricity
demand is expected to grow at 5.3 percent on average during 2015 – 2034. In
addition, peak demand levels are expected to grow at an average of 4.7 percent.
The current installed capacity is 3,900MW and it is expected that the total
installed capacity will need to be increased to 4,955 MW by the year 2020.
Kumarasinghe said, the power plants listed in the LCLTGEP for the period 2017 –
2020, should be immediately constructed and commissioned.
The CEB proposes to increase
the share of renewable energy capacity to 972 MW by 2020, which
would contribute 20% to the total power generation. Renewable
energy’s share in power generation is expected to peak in 2025
at 21.4% with an installed capacity of 1,367 MW. |
The CEB has proposed the setting up of two thermal power plants with a capacity
of 170 MW in the Southern region, 105 MW gas turbines, 300 MW natural gas power
plant and several renewable energy power plants with a capacity of 700 MW which
include three major hydro power plants.
500 mw deficit
Energy expert Kamani Jayasekara, former Deputy General Manager at the
Transmission and Generation Planning division at CEB, warned that by 2018 there
would be a deficit of 500 megawatts. “There is a margin for a surge in demand,
but we have little reserve in the system to balance it,” she added. This load
shedding she says, will ultimately lead to power cuts that would be unstoppable
and impossible to rectify instantly.
Earlier this week, President Maithripala Sirisena launched a new program aimed
at adding 220 megawatts of renewable solar energy to the country’s energy grid
by 2020 to meet at least 10% of the nation’s energy demand. When launching the
initiative the President said, the country was committed to meeting growing
energy demands with environment friendly options.
The CEB proposes to increase the share of renewable energy capacity to 972 MW by
2020, which would contribute 20% to the total power generation. Renewable
energy’s share in power generation is expected to peak in 2025 at 21.4% with an
installed capacity of 1,367 MW. Between 2025 and 2034, the share of renewable
energy in power generation is expected to reduce marginally from 21.4% to 20.0%.
A director at the CEB who did not wish to be identified said, the CEB was not
keen on pursuing sources of renewable energy, unless it was a directive from the
government.
“These are intermittent resources and we have no intention of clogging an
unstable national grid unless we have enough power plant to back it up in case
it falters,” he said. “We have stipulated a limit and will not transgress it by
inviting or including many plants.”
The source added that from the time the CEB announced high tariffs for
renewables, there had been a lot of pressure to include more renewables, not for
the sake of clean energy but ‘for dirty money’.
“At present only 20% of the total energy demand can and will be catered to by
renewable sources,” he said. “Everyone has forgotten that we were generating
100% of our energy from renewable from hydro.” He added that many of the
proposals received by the CEB were not technically or economically sound.
CEB Plan
Although the PUCSL has granted conditional approval for the (LCLTGEP) 2015-
2034, the Commission observed that the CEB will need to submit a new LCLTGEP for
the year 2018-2037 for the approval of the commission by April 30, 2017 in
keeping with the government’s policy on energy.
“The plants beyond 2020, mentioned in the 2015- 2034 Plan, should be revalidated
with the 2018- 2037 plan, in keeping with government policy,” Kumarasinghe said.
“The LCLTGEP 2018-2037 will need to be submitted to the Commission based on
wider stakeholder consultation.”
He added that the PUCSL expects the CEB to consider demand side management and
inculcate more electricity from renewable energy sources.
The Institution of Engineers Sri Lanka (IESL) a premier Engineering institution
in the country warned that power shortages were imminent and that consumers
would have to pay higher prices.
“The country is in danger of going back to the era of power cuts coupled with
higher prices of electricity. The growth in electricity sales has recovered from
the low 1% in 2013 to reach 7% in 2015; growth indications for 2016 are even
higher. In this backdrop, it is concerned that currently there are no major
power plants being built, to meet the growing demand,” an official communiqué
said. “The decision by the Government to change to LNG, can cause inevitable
delays. This change would result in the carrying out of fresh feasibility
studies, preparation of bankable project documents, obtaining necessary approval
and re-negotiating agreements.”
Expensive LNG
They also predict that change of fuel to Liquefied Natural Gas (LNG) would cause
electricity production costs to increase by 40-50%.
LNG prices they say, have declined owing to surplus in production and the
depressed oil prices, to which most LNG contracts are linked. Recent contracts
to supply LNG have been reported to be as low as 8.5 USD/million BTU.
The power sector engineers called upon the Government to scrutinize prices and
pricing formulae, and forecast quantities required, through expert studies,
before building LNG terminals. Such terminals require significant investments
exceeding USD 500 million. In any case, it would not relieve Sri Lanka from the
grave power crisis expected by 2018. |