Where indigenous experts are at work
Flyover at Orugodawatte nearing completion:
By Indeewara THILAKARATHNE
[email protected]
Chinese workers are busy along with their Sri Lankan colleagues at
the construction site of the to flyover at Orugodawatte junction which
is one of the main gateways to the city of Colombo. The construction of
the fly over has been continuing for over a period of nearly three
years.

Construction site of the Fly Over at Orugodawatte
Pix : Chinthaka Kumarasinghe |
The construction was, some what, delayed primarily due to diversion
of water, electricity and telecommunication underneath the road where
the foundation for the fly over was to lay.
Lands that came under construction had not been cleared out. Still
two lands including a temple has yet to be vacated.
According to the Consultant Engineer D.S. Dantanarayana, since the
commencement of construction, a considerable time had to be devoted to
diversion of underground network of main pipe lines which supply water
from Ambatale to the city of Colombo. Since the non-availability of a
map on laid out pipe lines, it had been a meticulous task to trace the
pipe lines.
“Although we are going ahead with constructions, before opening the
flyover in January, we have to get these two lands cleared. Two water
mains are running through this road from Ambatale to Colombo. The supply
of water to the city of Colombo can not be disturbed. Generally water
supply was disrupted once a month so it took a longer time for the
diversion. There are 33,000 KW, 11,000KW and 400KW high tension
electricity lines. As the same land to be used for the diversion, these
electricity lines had to be shifted before water mains were diverted.
Same procedure had to be adapted with regard to diversion of
telecommunication cables.
In order to facilitate piling on either side of the railway line,
railway lines have to be diverted to the next service line.
Railway lines were diverted ten days ago. “said Consultant Engineer
D.S Dantanarayana describing the obstacles that eventually delayed the
commencement of the constructions.
Although the project was planned to finish by September, 2008,
construction can be completed by January 2009. “If we could complete the
fly over by January 2009, it will be a real achievement “said
Dantanarayana, citing constrains under which Chinese constructor China
Auto CAIEC Ltd has to carry out the constructions.
The Flyover is designed to last for 120 years according to Sri Lankan
regulations. Special mixture of concrete has been used for the
constructions in order to withstand heavy loads.
“We are grade 60 concretes which is a very high concrete, for the
constructions. Actually, in the concrete mixture, we had silica fumes
from the coal ash to enhance the strength of the concrete and to improve
certain properties.
Usually we need, at least, fifteen nuton millimetre squire strength
in about four to five days times because we are stressing the beams up
to the maximum load to complete the project. Normally this process would
take fourteen days. But we are expediting the process with a special
concrete mix.
Here we use pre-stressing techniques to pre-stress box-beams and each
box girdle is hundred and twenty tones weighed and each beam is stressed
with a force of about thousand seven hundred tones.
The flyover consisted of four beams. Total width of the beam will be
about 4.3 meters. “said Engineer Dantanarayana of the techniques used
for the constructions.
The technique of pre-stressing was introduced by Sri Lankan engineer
Dr. Kulasinghe and Chandrasena fifty years ago. Subsequently the
technique was adapted by countries like China, Japan and Australia.
However, the technique is not widely used in Sri Lanka. For the
construction of the fly over, Chinese machinery and technology have been
used as it has substantially cut down the expenses. Chinese contractor
China Auto CAIEC Ltd is operating under the technical guidance of Sri
Lankan Engineers.

Construction site of the Fly Over at Orugodawatte |
Among other things, the project has, once again, proved beyond doubt
that Sri Lankan Engineers are as capable as their American or Japanese
counter parts in living up to targets and confronting with challenges.
“Our company is a State -owned company and commenced this project in
2005.
But we encountered several problems such as clearing up lands for the
constructions. Constructions delayed as a result of service diversion
and if everything was cleared for constructions, we can complete the fly
over in one year’s time.
According to our new construction plan, we suppose to complete the
flyover by the end of January 2009. We are also working on Kirulapona
Bridge and on Trincomalee Bridge.
Even in China, we do not use big beams as the beams used for this
project, “said Qi Cheng Fa of China Auto CAIEC Ltd.
Although the flyovers are quite new to physical surrounding in Sri
Lanka, they have been a regular feature in developed countries. The aim
of the flyovers is ensure an efficient network of roads easing the
traffic, thereby saving much -needed time and energy.
Government has decided to construct seven flyover within this year to
ease the traffic congestion in the city of Colombo.
Accordingly, Fly Overs will be constructed in Nugegoda (261m),
Kohuwala (219 m), Dehiwala (335m), Junction of Rajagiriya and Welikada,
(555m), Panadura (288m) Kelaniya South (300m) and Kelaniya (North) will
be constructed at a cost of Sterling Pounds 33 million. The project is
funded by the UK Government.
The construction of fly over at Nugegoda is also about to complete
and it will also ease the traffic in High Level road.It is a home truth
that nation can not march for a rapid development without basic
infrastructures such as efficient system of transport, cheap electricity
and excellent telecommunication facilities.
|