Moragahakanda - Kalu Ganga project ahead of schedule
By Shirajiv SIRIMANE in Moragahakanda

President at the ground breaking ceremony |
The Moragahakanda - Kalu Ganga development project, the biggest multi
purpose development venture undertaken by the government is progressing
ahead of schedule.
It's very saddening to note that Moragahakanda - Kalu Ganga
development project was first discussed in 1955 and again in the 1977
when the Mahaweli projects were being implemented. However, this venture
was scheduled for another 30 years before it finally took off the ground
as fulfilling an election pledge under the Mahinda Chintahna.
The local inputs added to the project are saving millions of funds to
the country and also is making faster progress.
The key role is being played by the Mahaweli Authority of Sri Lanka
which has a track record of building and maintaining Sri Lanka's biggest
dams, power and irrigation projects such as Kotmale, Victoria,
Randenigala, Rantambe, Maduru Oya and many similar ventures.
The Moragahakanda - Kaluganga development project comprises the
building of two main dams and they are being supported by saddled dams.
Project Director, R.D. Tennakoon said that the first saddled dam will
be completed by the end of this year and it was built entirely by local
engineers. "This is a 21 meter tall, 200 meter long earth dam and with a
width of over 7 meters," he said.
Local manpower

The saddled dam to be completed by end of the year

The new road under construction |
Tennakoon said that they also made it a point to use manpower from
the area thus ensuring a better money flow to the residents even during
the construction period. "We only have to complete the rip rap
(installing rocks on top of the dam to break waves) and rock for this is
being taken from the location itself," he said.
Project factfile

* Location:
Central and North Central
Provinces
* Project Configuration
- Construction of two major
reservoirs, Moragahakanda and Kaluganga
- A conveyance system
consisting of two tunnels and transfer canals and
- A power house of 20 MW
installed capacity.
* Objectives:
- To provide irrigation
water facilities to 81,422 ha in the Dry Zone
- Potable and Industrial
Water Supply to Anuradhapura and Trincomalee towns
- Generation of electricity
by hydro power Principal Project Features
Moragahakanda Reservoir
* Type of Dam:
A roller compacted concrete
main dam and two rock fill saddle dams.
* Maximum dam height:
65 metres
* Active Storage:
521 million cubic metres
Kaluganga Reservoir
* Type of Dam:
A rock fill main dam and two
saddle dams, one rock fill and the other earth
* Maximum Dam Height 67
metres
* Active Storage 144 million
cubic meters Environmental Management Plan
(a) Reforestation of about
2000 ha in the Amban Ganga Basin
(b) Clearing of elephant
corridor between Giritale - Minneriya nature reserve
(c) Habitat enrichment in
proposed corridor between Wasgamuwa National Park and
Victoria - Randenigala - Rantambe Sanctuary
(d) Research and development
in the proposed corridor
(e) Establishment of a 100 m
wide reservation around the reservoirs
(f) Rehabilitation of tanks
in adjacent nature reserves
(g) Establishment of
electric elephant fence around the resettlement area
 |
He said that resettlement had been one of the priorities in
implementing this project and in addition to the Mahaweli Authority the
donor countries too are very keen on this. "Hence we have talked to the
residents and are offering them two and a half acres of land suitable
for cultivation and another half an acre for residential purposes. This
is in addition to the compensation they would receive," he explained.
The Mahaweli Authority has been having a very good track record of
resettlements, an experience they gained through the previous ventures
and this success story would be adopted here as well.
"We have also gone a step ahead and after paying compensation for
their lands, buildings and cultivation. The Authority will allow them to
take building material and even timber from their old premises," he
said.
"We want to ensure that they are happy and even during the
resettlement period we will provide them with some rations and assist
them with the cultivation." He explained that 1,581 families in
Moragahakanda area and 787 families in the Kalu Ganga area have been
earmarked to be compensated. This will commence from 2012 and would be
completed in two years. "Over 90 percent of these people are farmers and
no major town or archaeological site is coming under water due to this
project."
Model farm aid
Technical advice too would be provided while the Mahaweli model farm
which is now being constructed would give them hybrid seeds and plants
for agriculture. The construction of a new township which is the apex of
the Medirigiriya development plan, as well as tanks and the road network
are being expeditiously completed.

Project Director, R.D. Tennakoon at the site |
Once implemented, the 10 1/2, kilometre Naula-Elehara Road will be
submerged. A new carpeted road is being built along the new reservoir.
In addition a new 26 kilometre road too is being built linking the
proposed new resettlement area.
Due to this project there would also be a flood control system which
would be another advantage.
Protecting the environment too had been a priority and the Authority
is taking meaningful steps in this regard which also include the
constructing of an elephant corridor. Even endangered species and trees
are being relocated.
The total cost of the project has been estimated at around Rs. 6.5
billion. The funding for the Kalu Ganga project is being channelled
through the Kuwait and Saudi Arabian governments as well as from the
OPEC Fund. JAICA from Japan is funding the Moragahakanda project.
The project aims to irrigate 81,422 hectares in the Central and North
Central provinces benefiting over 100,000 families, in addition to
providing drinking water and generating hydro-power.
One of the major plus point of this multi purpose development venture
is the ability to generate 20MW to the National Grid. Annual fuel cost
savings with the hydropower produced will be around US $ 2.49 annual
average.
Benefits Northern farmers
The direct benefits include increased rice yield per hectare with an
additional agricultural production of 109,000 tons annually. The net
annual agricultural benefit will be US $ 27.7 million in financial
terms.
Lahmeyer International from Germany in association with the Central
Engineering Consultancy Bureau (CECB) of Sri Lanka, United Consulting
Group (KUWAIT) and Chuo Kaihatsu Corporation, Japan has conducted
studies for the project and have taken great pains in this regard.
Once the Moragahakanda project is completed a large number of farmers
in the Northern part of this country will benefit, said Director
General, Mahaweli Authority, D.M.C. Dissanayake.
He said that under the second phase of Moragahakanda project a
channel named `NCP channel' will be constructed up to Iranamadu. This
would be a 100 kilometre channel and would be Sri Lanka's longest
channel.
The completion of the Moragahakanda reservoir project will increase
the island's agricultural productivity from 165 percent to 185 percent,
with a total output value of US$ 17 million.
The average annual fish production potential of the reservoir is
estimated to be around 4,700 tons per year, representing a net benefit
of US $ 1.67 million annually. Farmer income is expected to increase by
80%, once the Moragahakanda reservoir project is completed.
It is also expected to save US$ 2.2 million, locally, by supplying
water to households and for industrial purposes.
The Mahaweli Project is the largest Multi Purpose Development Project
ever undertaken in Sri Lanka. The Mahaweli Master Plan drawn up during
1964 - 1968 for harnessing the waters of the Mahaweli envisaged the
development of 365,000 ha for agriculture and installation of 600 MW of
Hydro-Power capacities. The total Mahaweli Project Area covers 39
percent of the whole island, 55 percent of the Dry Zone, and encompasses
60 percent of the irrigable land area of Sri Lanka.
Minister Nimal Siripala de Silva affirms that the government has
planned to complete the Moragahakanda and Kalu ganga irrigation project
by year 2014.
People have being talking about King Parakramabahu for centuries for
constructing the Parakarama Samudraya. The Moragahakanda - Kaluganga
development project would be four times bigger than the Parakrama
Samudraya and people will talk about this project for a longer period
than the Parakrama Samudraya.
|