Multiple benefits offered to villagers:
Deduru Oya Project takes shape
By Shirajiv SIRIMANE in Deduru oya

 |
 |
Co-Project
Director, Sunil Perera |
Deputy
Director Planning, Malani Kulasinghe |
It's not at all an exaggeration that it took more than 20 years to
resettle some families and pave the way to get a multi-purpose
development project, Deduru Oya off the ground.
The Deduru Oya development project brings multiple benefits, not only
to the entire North Western province, but to other neighbouring areas as
well.
The severe drought in 1960 prompted the villagers in the area to
request for an irrigation project for the North Western Province (NCP).
At every general election an irrigation project for Wayamba (NCP) was
promised. However, they had always been confined to promises.
Another promise was made in the 1980s with plans being drawn and even
funds mobilised. However, the families who would have to be relocated
protested and successive governments bowed down to this pressure,
conveniently ignoring the benefits the project would bring the
community.
Project at a glance
District :
Kurunegala, Puttalam
River :
Deduru Oya
Area to benefit :
7100 ha (Existing), 1600 ha (new)
Estimated cost :
Rs. 6,200 million
Project duration :
2006 2013
Design and
construction:
Irrigation Department |
One reason for the families to protest was that they owned fertile
land (unlike in Norochcholai where the power plant was built) and did
not want to lose them. Another reason was that the villagers feared that
they would not be given similar land and that compensation would not be
paid.
Compensation
Three years ago, the then Minister of Irrigation Chamal Rajapaksa
took a bold decision to go ahead with this project. He managed to
successfully convince the people and finally move them out. Resettlement
was a major issue even three years ago as there were organised,
politically-motivated protests.
However, today, more than 60 percent of the project has been
completed with the families being provided alternative land and
compensation being paid. Some families received over Rs. 3 million to
relocate and were also given the option of taking all their belongings
with them. Each family was provided with a half-an-acre block of land, a
basic allowance of Rs. 8,000 and a monthly allowance of Rs. 6,000 up to
six months.
They were even granted permission to cut trees and use the timber.
Today, the very people who protested, are happy and content.
The families were paid Rs. 500,000 for each acre of coconut and Rs.
300,000 for an acre of paddy. Project Director of Resettlement, W.
Tilakaratne Bandara said that 220 families have been resettled so far.
In addition, infrastructure facilities including electricity and
roads have been provided for the benefit of these families.
100% local venture
Deduru Oya is designed as a multi-purpose development project. It
would provide water for agriculture for over 28,000 acres of irrigation
land in the Mee Oya and Deduru Oya basins.
It would provide safe drinking water for 50,000 families,
automatically raising the health standards in the area. It would also
add 1.5 megawatts of power to the national grid.
One of the salient features of this project is that it is 100 percent
designed and constructed by local engineers attached to the Irrigation
Department, once again proving the local engineers' capabilities.
The total investment for the project is Rs. 6.2 billion and the
second most important point is that this is totally funded by the
Government with local funds.
King Parakramabahu had once said that not a single drop of water
should flow to the sea without being used.
However, it was sad to see over 1,000 million cubic metres of water,
just flowing to the sea, via Sri Lanka's sixth largest river, Deduru
Oya, without being put to any proper use.
This was also another reason for the launch of the Deduru Oya
reservoir project.
The main dam of the Deduru Oya scheme is being built in Thun Modera,
just below a point where three rivers meet, thus ensuring that there
would be water at all times.
The dam would be built to store 75 million cubic metres of water and
the water storage area is 5,000 acres.
The dam would be 18 metres in height, nine metres in breadth and
2,400 metres in length.
The core of the dam consists of concentrated clay and this was a
technique used by ancient kings to make the dam last for centuries.
The use of clay reduces the impact of water on the dam.
On target
The dam of Deduru Oya is now 90 percent complete and both the Left
and Right Bank canals (LB) (RB) too are nearing completion. Over 50
percent of the financing too has been completed, said the energetic
Co-Project Director, Sunil Perera.
The LB sluice would be 15 feet in breadth and 44 kilo-metres in
length.
Abandoned tanks
Due to the lack of water, farmers in the area were only able to grow
paddy during one season. However, with the commissioning of the Deduru
Oya LB canal, 6,000 acres of paddy land would be cultivated during both
seasons.
Both canals would also feed the ancient tanks which only depended on
rain water, thus ensuring that cultivation could be carried out in both
seasons. "The Deduru Oya LB project would restore eight old tanks",
Perera said.
The RB canal, while reactivating ancient tanks, would even provide
irrigation water to the Iginimitiya reservoir, which had failed to
provide irrigable water during both seasons and is somewhat a failed
project.
"The Iginimitiya reservoir is located at an almost similar elevation
as the Deduru Oya reservoir and it was a challenge to take water along
the RB canal to the bank. We used special gradient techniques and the
entire 33 kilometre LB canal was made with concrete", he said. He said
that with the reactivation of the Iginimitiya reservoir, in addition to
paddy over 1,000 acres of cash crops would also be grown.
"We will also give water at several points in both LB and RB channels
upon requests made by farmers."
The Deduru Oya project would also help reactivate the natural
under-ground water systems and most importantly, put a stop to flooding
in the area. "Great pains have been taken to maintain the small water
streams and we have sometimes used underwater pipes to feed them, to
maintain and refresh the ground water table system", Perera said.
He said that this project ensures that the existing water supply in
the Deduru Oya would not run dry and it has no environmental impact. "As
the project fills ancient tanks, it would be highly beneficial."
He said the soil that was extracted while constructing the LB and RB
canals were used to fill the ground and lower elevated land.
Another important aspect is the growing of tress and grass to stop
erosion in the LB canal and the inundation area.
Purification plant
The National Water Supply and Drainage Board will start construction
of a water treatment plant to provide drinking water to over 50,000
families next year. This project would be ready by 2013.
Perera said Director General of the Irrigation Department Dr. G.G.A.
Godaliyadda is personally supervising this project and is a tower of
strength to them. Deputy Director Planning, Malani Kulasinge said that
this would help the families who had to walk several kilometres to fetch
drinking water.
They would now have peace of mind and most importantly, time to forge
ahead on self-employment projects, thus bringing them additional
revenue.
The Ministry of Power and Energy will undertake the construction of
the 1.5 megawatte power plant next year.
It's ironic to note that over 200 villagers work in this project,
including some of the protesters.
One worker who was sceptical about this project said that they were
misled, but are now opening their eyes and seeing the benefits that
would come their way due to the project.
|