Much awaited power to see the light of day
by P.Krishnaswamy
The much-awaited and sorely needed power for the national grid from
the Upper Kotmale Hydro Power Project (UKHP) will be commissioned next
week, Project director Shavindranath Fernando told the Sunday Observer
yesterday.
Initially one machine generating 75 MW power and the second
generating another 75 MW power, will be commissioned after two months
adding 150 MW power to the national grid, he said.
Although the project was due to be launched in the 1980s, it never
saw the light of the day due to political expediency and various other
reasons, until President Mahinda Rajapaksa took the bold decision in
2005 to proceed with construction work of the project.
All intricate aspects of the Japanese-funded Rs.40 billion project
have been minutely examined before it is commissioned soon,
Shavindranath Fernando said.
The project was meticulously planned and executed to adequately
address all concerns regarding environment, bio-diversity, displacement
of families and the preservation of the landscape and its natural
beauty, he said.
The test-filling of the reservoir was completed in December last
year, followed by its connection to the national grid and a test run.
The Overseas Economic Cooperation Fund (OECF) of Japan funded the
conceptual design, environmental impact assessment and the final design.
The project was completed under several phases. The project has the
longest mountain tunnel in the country-13 kilometres.
Four-hundred and ninety-five families, mostly plantation Tamils, who
were displaced under the project have been resettled in modern housing
units with compensation and livelihood facilities, the Project Director
said.
|