Construction industry development Act takes a U turn?
by Dr. Chandana Jayalath
Any construction project would encounter commercial, contractual,
technical, interface or interpretative issues and in some instances, the
parties are unable to resolve conflicts, may be because the contract is
ambiguous or silent. As a result, disputes arise unless they are
addressed at the earliest practicable opportunity.
Sizeable construction issues, claims and disputes make a considerable
impact on the most needed harmonious relationship between the employer
and the contractor. Claims once turned into disputes are expensive and
time-consuming.
Employers suffer loss of income, problems with funding and delayed
occupancy while contractors face financial instability due to delays in
payments. There will be parallel claims against each other, such as time
extension and liquidated damages, particularly when the parties are at
extreme ends.
Disputes
The new Construction Industry Development Act has, in a couple of
provisions, introduced a way of settling disputes related to
construction activities by setting parameters in the form of a
hierarchical gauntlet.
Accordingly, if the parties so desire any dispute relating to a
contract for construction works, if it is not provided for in the
contract, may be settled through conciliation or mediation.
However, there is 'ha-ho' among the stakeholders of the construction
industry on the lack of care, misconduct and competency of the
conciliators, whether in-house or external.
Among the allegations against them are the failure to attend to an
agreed time frame and incompetence causing the parties to walk off at
will.
Complaints also include incorrect advice, failure to prevent the
parties making an unfair or unworkable agreement or failing to disclose
to a party that they were threatened with harm in circumstances where it
would be reasonable to expect disclosure.
Another complaint is that the conciliator made an unnecessary
interference, applied duress or misled a party in some material way.
As with judges, conciliators have to act impartially and
independently without fear and favour. Independence allows creativity
and flexibility towards an amicable settlement. Lack of independence
makes conciliating a given dispute an impossible task.
Hence, conciliators should be free to conduct conciliation as they
think appropriate and should not have the fear of being sued for an
error or future harassment. The Construction Industry Development
Authority Act has failed to provide at least a quasi immunity status to
conciliators, to enable them to avoid trial of a claim against them.
In England, and many other countries, judges retain absolute immunity
for their independence in line with the policy to protect the citizen
while extending the same to others engaged in the administration of
justice such as witnesses, counsel, Court clerks, the jury and Court
appointed mediators.
The Act also states that mediation is a free choice on the part of
the disputants. It is the parties who choose whether to remain at the
mediation proceedings and whether to enter into an agreement.
In theory, a mediator as a neutral, cannot influence the outcome of
the mediation, exercises a non-determinative role and, therefore, there
is no basis for mediator liability. The fact that the mediator is not
responsible for the outcome of mediation is the very reason why they
should not be liable for any actions based on the terms of any agreement
entered into at the mediation.
Conflict
On this basis, it can be argued that mediators should also be immune
from any civil action arising from the substantive outcome of the
mediation for example unfavourable bargains or loss of opportunity.
Mediation with an evaluative orientation may be necessary whenever
there is a monetary charge to the conflict and if the conversation
becomes hostile or if the disputants are constantly repeating their
positions, halting the progress of the mediation.
The evaluative style is also better suited for resolving disputes
where one or more of the parties appear unreasonable or inflexible in
its negotiating position.
It detects where the parties truly stand, drives the mediation
forward and explores settlement possibilities from different angles and
finally establishes a basis of amicable settlement, as exactly intended
in construction mediation.
If mediation is to be a true form of dispute resolution, its
underlying theory must also be distinguished from traditional Courts and
other forms. Neutrality being a principle cannot however sacrifice
fairness, in process and outcome.
'Neutrality' doesn't mean that the mediator does not have a point of
view or even a solution which he feels would work.
Rather, neutrality in the mediation context means that the mediator
is not supposed to impose his or her views on the parties.
Neutral is no good without subject matter expertise and construction
clients do believe it is indispensable. The rationale is that the
mediator brings industrial know-how and exposure that invariably
benefits both parties.
As per the new Act, a party to any contract relating to an identified
construction work, if unable to settle any dispute by conciliation or
mediation by the Authority, that is CIDA, may refer such dispute for
adjudication.
The Authority shall maintain a Register of Adjudicators competent to
adjudicate disputes in the form and manner as may be determined by the
rules made by the Authority. Two years ago, a pool of construction
adjudicators was set up at the ICTAD.
Adjudication is a unique process for resolving construction disputes
arising under construction contracts with the primary purpose of
relatively straightforward fast tracked resolution.
In essence, adjudication is a process where a neutral third party
gives a decision, which is binding on the parties in dispute unless or
until revised in some other manner such as arbitration or litigation.
The binding effect of an adjudicator's decision is made clear in
Standard Bidding Documents issued by the ICTAD.
An adjudicator's decision continues to be of effect even though a
party has applied for arbitral review of the decision or any other
proceeding has been launched.
While it can be seen that adjudication does not necessarily achieve a
final settlement of any dispute because any of the parties has the right
to have the same dispute heard afresh and determined in arbitration if
the contract provides for it, the empirical evidence to date indicates
that the majority of adjudication decisions have been accepted by the
parties as the final result.
Adjudicators are allowed to conduct proceedings as he or she sees fit
within a procedural and ethical framework. The role of an adjudicator is
wholly different from that of a solicitor who prepares a client's case
for trial.
The solicitor prepares a one-sided case for argument in Court. The
adjudicator, on the other hand, has to read the files, interview the
parties, visit sites and then arrive at his decisions. The adjudicator
has to provide reasons for his decision, unless otherwise stated.
It does not, however, state that reasons should be part of the
decision, but could be provided separately to the decision. The
adjudicator shall adduce evidence or invite technical arguments from the
parties by asking questions either at a hearing or in correspondence,
giving both parties the opportunity to answer.
Hence, the adjudicator has an inquisitorial role by ascertaining the
facts and the law. The adjudication process is relatively simple and
robust. However, time constraints on all parties and the adjudicator and
the consequences of any failure to comply with those constraints may be
severe.
An Appeals Board has been introduced in the Act for those who are not
satisfied with the adjudicator's decision. An Appeals Board consisting
of not more than seven members will be appointed by the Minister upon
the recommendation of the Authority.
All members of the Appeals Board shall be qualified persons as
specified in this Act with not less than twenty years of experience in
the field of construction.
Any person who is aggrieved by a decision of the Authority may appeal
to the Appeals Board in the manner as shall be prescribed.
After the hearing of an appeal, the Appeals Board shall give its
decision within two months from the date on which such appeal was
received by the Appeals Board and may confirm, vary or reverse the
decision appealed against.
The decision of the Appeals Board and the reasons, therefore, shall
be notified in writing to the appellant and the Authority.
Any person aggrieved by the decision of the Appeals Board in respect
of any appeal may appeal against such decision to the Court of Appeal
within thirty days from the date on which the decision and the reasons,
were notified to the appellant.
What is apparent with the foregoing is a way towards the Courts of
Law away from conciliation, without a stopover at any arbitral tribunal
that has been in practice over five decades.
The Arbitration Act of Sri Lanka No. 11 of 1995 provides for a
legislative framework for the effective conduct of arbitration
proceedings and the mechanism for the enforcement of arbitral awards
thereby making arbitration a viable and expeditious alternative to
litigation for the resolution of commercial disputes.
As stated in the preamble to the Act, one of its objects is to make
legal provision to give effect to the principles of the convention on
the recognition and enforcement of foreign award of 1958 (The New York
Convention), following to a great extent, the UNCITRAL Model Law.
The Sri Lankan Arbitration Act states that by an agreement any
dispute can be determined by arbitration unless the matter in respect of
which the arbitration agreement is entered into is contrary to public
policy or is not contrary of determination of Arbitration.
The dispute resolution clauses given by ICTAD specify periods within
which certain acts such as appointment of arbitrator have to be made.
The Arbitration Act does not specify time limits to carry out such acts.
DAB
FIDIC Condition 1999, that has been acclaimed internationally, has
introduced the Dispute Adjudication Board (DAB) system as a
pre-arbitration need.
Accordingly, disputes between employer and contractor should be
referred to the Dispute Adjudication Board as a pre-arbitral step before
reference to arbitration clause 20 of FIDIC 1999.
When there is no settlement before the DAB, the dispute can be
referred for arbitration. Due to the nature of some contracts, the
involvement of more than two parties in a single dispute can be seen,
e.g. involvement of employer, contractor and number of sub-contractors
in construction contracts and disputes relevant to them.
Arbitrators may keep away from giving written reasons for the award
and the final decision of the arbitrators will be a valid award.
However, if the parties do not agree, the arbitrators will give
reasons for the award under Section 25 (2) of the Arbitration Act of Sri
Lanka No. 11 of 1995.
One of the serious criticisms levelled against arbitrations in Sri
Lanka is the time factor. The arbitration agreement incorporated in the
ICTAD contract under clause No. 67 stipulates that the period within
which the award should be made is four months.
Although the Arbitration Ordinance of 1948 stipulated three months,
the present Arbitration Act does not specify a time limit. Parties are
free to fix a desired period for proceedings.
According to the arbitration agreement recommended by ICTAD, the
period for commencement of arbitration may take a maximum of 90 days and
in accordance with the FIDIC documentation, the maximum period to
appoint an arbitrator is 154 days.
Hence, the time factor remains a major drawback in the arbitration
process. However, there is no clear reason as to why the new Act did not
pursue arbitration although Sri Lanka is a signatory to the 1958
Convention on the Recognition and Enforcement of Foreign Arbitral
Awards.
The Act of CIDA provides that any person aggrieved by the decision of
the Appeals Board in respect of any appeal, may appeal against such
decision to the Court of Appeal within thirty days from the date on
which the decision and the reasons, therefore, were notified to the
appellant.
Inter-alia the Courts' primary role is to make, interpret and define
law and safeguard the public interest and social values.
Courts interpret what the documents depict in terms of true intent
the parties had in their minds at the time they entered into the
contract. Courts may eventually rely on court-appointed experts in the
context of highly technical issues, ultimately generating a vicious
circle of dispute resolution.
For any alternative method to be truly voluntary, Courts should use
discretion only when the will-power of the parties remain.
The outcome would still vary on the Court's persuasiveness such as
any sanction that makes participation and conduct of the process
obligatory which will restrict the choice of the disputants.
Methods
On the other hand, Courts should be sensitive when power imbalances
exist, not necessarily to protect the parties' rights but to leave
enough room for self-determination.
When tapping the potential of these techniques, Courts should first
test the appropriateness, resistance and willingness before encouraging
and facilitating dispute resolution.
It will help secure key characteristics of alternative methods such
as participation in good faith, autonomy, choice and self-determination.
On the contrary, mandating alternative means without consent of the
disputed parties or court connected means with imposed rules such as
strict deadlines may dictate the outcome and prejudice the aim of
laissez-faire amicable settlement.
What the parties need is, therefore, something that works well,
indeed works faster, cheaper and in a much less contentious manner than
traditional tribunals.
Parties strongly believe in a process in which the parties retain the
right to decide the outcome of the dispute rather than a Court order or
an Appeal Board decision.
Under such circumstances, the Act would have allowed an
extracontractual opportunity for the parties to revisit their concerns
at any point of the settlement gauntlet, for example a third
intervention, a neutral approach where the lay employer refers the
matter to a third neutral who will first evaluate the case independently
and recommend a solution or option that best fits the party's needs, yet
within a contractual framework.
Fair assessment
For example, in Qatar, today, the parties seek a nominee to review
the disputed issues and consider it an extra 'contractual' opportunity
to get their disputes settled at the employer's level. Such an
arrangement in fact avoids the formalities in arbitration or litigation
in toto.
Almost all the cases have been successfully handled within a
contractual framework as mentioned, taking all the circumstances into
detailed consideration, resulting in fair assessment acceptable to all
the parties.
Accuracy, accountability, short response time, cost and time savings,
increased awareness of the issues and increased dependency could be a
reflection of success, as a dispute mechanism.
Parties who act in good faith are likely to comply with a
recommendation just as they would accept a decision anyway.
At present the District Courts in Sri Lanka and the two Commercial
High Courts in Colombo are unable to cope with the large volume of
cases.
The result is that Courts are not in a position to dispense justice
expeditiously to litigants who have sought recourse to the Courts.
Construction claims tend to be of the most technical nature -
intensive and multifaceted than most other commercial disputes.
The construction industry needs a fast and cost effective means for
dispute resolution.
The Act should have given enough emphasis on the concept of 'internalising'
disputes via mediation instead of focusing on traditional, highly formal
and rigid procedural techniques. |