Mega projects cost overrun: a vicious techno-political cycle
by Dr. Chandana Jayalath
The topicality of cost overrun has been accentuated moreover by the
political allegations against the previous regime than by strict
evaluation from an apolitical point of view.
A gamut of technical, economic and political reasons may together
matter for cost overrun in any typical construction project,
particularly when they are large and complex.
The first and foremost reason behind cost overrun is the inaccuracy
of cost estimates. Forecasting project cost is a critical management
function in tracking and controlling the cost of construction projects.
Advising the owners or managers of possible higher costs at the
beginning must be accompanied with the associated economic, technical
and locational limitations.
A cost plan should carry several options of making changes where
possible and maintaining budgets. Unfortunately, this aspect of early
cost advice in the establishment of ball park figures has been a
neglected skill.
Plan
Further, the designs that form the basis of the project may not be
realistic where a combination of specified features is difficult to
achieve or that drawings show an incorrect arrangement.
Executing a project with no exact need laid down in precise terms
will either end up with extra costs or cause problems that can only be
resolved later at additional cost.
Planning is the next in line where the project should progress
according to a plan that assigns durations to project tasks. If the
projected durations are too short due to the will of politicians, then
the project may take longer than anticipated and cause cost overruns.
Monitoring project tasks on the critical path, which is the task
sequence from project start to finish that takes the longest to
complete, helps reduce delays.
Project tasks off the critical path have slack times, or free times
between tasks, that can be used to compensate for delays.
Changes in the scope of supply within a project also cause cost
overruns. These changes generally result from new needs that the owners
fix for quality, performance and workmanship that may not work at all.
It is important that the owners understand that additional needs
result in higher costs, whether it is classified as improvements or
otherwise.
Since the blue print to achieving good technical input to project
execution are usually mapped out on the basis of project designs, a
design with errors practically means wrong or insufficient
representation of project deliverables.
This will lead to wrong application of techniques in achieving
results. As the actual execution phase of the project will reveal the
errors and attempts to correct it will lead to delay and cost overrun.
Design errors could also crop up if project estimations are done on
the basis of designs having errors of omission thereby leading to extra
work and change of order.
Claims
Similarly, designs that are done without extensive investigation of
site could entail potential errors.
Claims are the other side of the same coin. In foreign funded
projects, claims specialists having a proper quantity surveying and
contract administration background are mobilised on the projects even
before construction commences.
Their sole task would sometimes be to locate loopholes in the
documentation and look for lapses in the process of contract
administration.
This 'loophole engineering' facilitates 'juicy' claims and more
particularly, problems arise when the provision for claim is abused, for
example by allegedly tendering at low prices to profit out of others'
mistakes.
The political-economic explanations see cost overrun as the result of
strategic manipulation of scope or budgets by trying to do what
politicians desire. Historically, political explanations for cost
overrun have been most dominant in Sri Lanka.
Grounded in social psychology, this way of looking at cost overrun is
apparently because politically ruined organisations become entrapped in
a particular course of action, thereby throwing good money after bad to
make the venture succeed.
Bribes
Defying conventional rationality behind subjective expected utility
theory, termed 'sunk cost fallacy' where politicians attempt to justify
increased investment in a decision, based on the cumulative earlier
investment, despite new evidence suggesting that the cost, starting
today, of continuing the decision outweighs the expected benefit.
The sentiment underlying this fallacy can best be described as
'throwing good money after bad' such as in gambling.
From high ranking officials diverting funds, a known fact is that
corruption takes place in contracting firms offering bribes for new jobs
and technical officers approving bills on a commission.
On one side, this results in technically poor products, leading to
cracks, undulations and slips in road projects for example. While
corruption is very difficult to trace mainly because the parties only
deal with hard cash, it becomes a 'technical' cancer not easily
detectable when it is connected with the supply and demand side of the
construction means, processes and procedures.
Variation
For example, a bidder may have bribed the project owner's
representative to persuade him to award the contract to the bidder.
The two parties may also have agreed that the cost of the bribe would
not be included in the tender price, but would be fraudulently included
in the cost claimed for a large variation during execution of the
project.
A contractor may bribe the project owner's representative to persuade
him to issue an unnecessary variation which materially increases the
contractor's scope of work and which has an inflated price.
A contractor may bribe the engineer to persuade him to issue an
extension of time to the contractor, which is not contractually due.
A contractor may bribe the project owner's quantity surveyor to
persuade him to approve the interim bills with exaggerated figures. A
contractor may bribe the project owner's works inspector to persuade him
to approve defective or non-existent work.
Vicious cycle
Conversely, contractors may agree with contract administrators to
account for off-site materials which are not properly designated for the
project.
They may also offer bribes to facilitate approval of claims for
additional money or time where such claims are not properly justified
showing causes and effects.
These activities generate a vicious cycle of cost overruns.
Achieving error-free design entails good communication with the
entire design team and integrating a design process that is properly
planned, giving enough time for corrections, extensive investigation and
reviews.
Similarly, effective project planning and a controlling and
monitoring mechanism should be set up to enhance project cost
performance throughout the project life cycle.
Value management could be applied to obtain the best cost effective
design options. To achieve proper control for change of scope, it is
important to first identify the fact that change is inevitable and
desirable for the completion of the works and could equally be
beneficial to the success of the entire project.
In nutshell, cost overrun essentially warrants some kind of
whistle-blowing by disclosing correct information to the appropriate
regulators, police or the media about malpractices. Whistle-blowing is a
selfless act any citizen in the best interests of the public. |