Omissions and contractual obligations
Importance of ensuring omitting work due to lack of
funds is genuine:
by Dr. Chandana Jayalath
With the suspension of many large scale projects, its effect on the
supply chain is no less significant than the suspension itself.
Projects have been functioning on a given scope of work within which
the parties are geared, and indeed contractually obliged, to meet mutual
obligations.
A few may know that any decision, whether by the engineer or the
employer, to omit a part of the contract work saying there are no funds
and later get the same work done by another contractor whose allocation
meets this omitted part is as significant as a suspension from a strict
contractual point of view.
FIDIC, being the most acclimatised standard forms of contract widely
adopted in international contracts, recommends how omission can be made
in a contract.
The position is clear in the Yellow, Silver and Gold Books in the
FIDIC series wherein each states that 'A variation shall not comprise
the omission of any work which is to be carried out by others'.
Although the wording in the Red Book is not as precise, it appears to
be the clear objective.
The nucleus of the SBD (Standard Bidding Documents) series in Sri
Lanka issued by the ICTAD (Institute for Construction Training and
Development), has been based on the foregoing thinking and there is no
subtle difference in the interpretation.
Reasons
It would appear that this provision is included in FIDIC to prevent
the employer from awarding work to others, possibly because they could
save money by doing so or because the employer may have some interest,
commercial or otherwise.
Among the gamut of reasons may well be the lack of funds as funds
many have been fully exhausted allocated in that particular contract. In
this type of situation, many employers and engineers fail to realise
that the contractor is fully within his rights to bring a claim against
him for loss of profit or costs incurred if such an action was taken.
The standard FIDIC conditions do not contain any provisions that will
allow the engineer from omitting work from one contractor to give it
another contractor during the course of the project.
Unless the parties have agreed to do so, and work is omitted from the
contractor, it would clearly be a breach of contract.
Claims
It would, though, be prudent of the employer, that even if such a
course of action is open to him, to take care that he does not run foul
of other common provisions.
For example, in the Red Book, Clause 12.3, variations in price may be
claimed if the reduction in scope causes a change in the quantities of
materials of more than 10%, and so forth.
Additionally, some contracts may contain a provision where a change
in the total contract price beyond a certain percentage permits either
party to renegotiate the contract. Hence, if the removal is not about
cause but rather for the employer's convenience, then the employer could
most certainly expect a claim for loss of profit, overheads and so forth
from the contractor.
In case the Engineer instructs a variation through which a part of
the works will be omitted, the 'FIDIC 4th - A Practical Legal Guide - A
Commentary on the Internal Construction Contract' by Edward Corbett says
that the Contractor can challenge the instruction under clause 67
(Disputes) or can treat it as an abandonment under clause 40.3
(Suspension lasting more than 84 days.
If the contractor has been negligent in performance due solely to
reasons attributable to the contractor, then termination is possible
under the Red Book Clause 15 (the Silver Book appears to be the same).
All law jurisdictions, be it common or codified, need the omission to be
genuine and if not, it would be a breach of contract. |