New management dealing with massive fraud:
Hyatt Hotel project faces Rs 9b shortfall
by Lalith Fernandopulle
The report on the large scale financial fraud and mismanagement of
funds by the previous regime in the Hyatt Hotel project in Kollupitiya
and Hambantota will be presented to the Ministry of Finance to bring all
perpetrators to book, the new Chairman, Canwill Holdings Ltd., Hemaka
Amarasuriya, told the media last week.
A forensic audit into the Hyatt Hotels project in Kollupitiya and
Hambantota brought to light a staggering fraud committed by the
Rajapaksa regime which had doubled the initial estimates of the projects
from Rs. 13 billion to Rs. 27 billion and the company is now facing a
shortfall of Rs. 9 billion to complete the projects, the new board of
directors revealed.
Canwill Holdings Ltd., a state-owned entity set up by the former
regime was entrusted with Rs. 18.5 billion in equity funded by it
shareholders, the Sri Lanka Insurance Corporation, Litro Gas and the
Employees Provident Fund (EPF). Forty six percent of the shares were
held by Sri Lanka Insurance while the rest was between Litro Gas and EPF
“The new management will recapitalise the funds by going back to the
shareholders for further funding to carry on the project in Kollupitiya.
We will first focus on completing the Kollupitiya project and then think
of what should be done with the Hambantota hotel,” Amarasuriya said.
The 400-room city hotel is expected to give a complete facelift to
the city as a premiere global hotel brand that will cater to a niche
market.
Amarasuriya said the cost increased due to the Hyatt brand being
elevated to Grand Hyatt, the highest brand in the Hyatt family across
the world.
Amarasuriya said the tender procedures of the former management were
not transparent. Contracts were granted to people and parties as they
wished.
“Work on the project is progressing. The shell of the hotel has been
completed and currently the interior designing is being done.
We hope to complete the project by 2017, which is three years behind
schedule.
The Colpetty Hyatt has been under construction for the past three
years. The audits revealed massive wastage and mismanagement from the
outset,” Amarasuriya said.
Three additional properties were acquired by paying Rs. 40 million
above what what was suggested by the government valuer at the behest of
the company.
He said the former board did not have formal meetings and open
bidding for contracts. Around Rs. 300 million was spent on the
Hambantota Hyatt even before launching work on the project.The new board
has dismissed foreign consultants hired at staggering amounts. A foreign
engineering consultant was hired by the former management at Rs. 16
million a month.
“A former managing director had been issued a corporate credit card
with a limit of Rs. 1.5 million and his children were employed by
Canwill Holdings.
We have so far saved around Rs. 150 million by cancelling and
renegotiating contracts. We hope to save another Rs. 100 million by
cutting down waste,” Amarasuriya said.He said when completed Hyatt
Colpetty will be the best city hotel and the showpiece in Colombo.
The hotel will be occupied by high profile businessmen with meeting
rooms and facilities for board and transactional meetings. It will be an
attractive venue for weddings and other social functions.
“It is the task of the new board to expedite work on the project,
reduce waste and get adequate returns on the invested share capital,”
Amarasuriya said. |