Polpitiya: 20 years on, incomplete...:
A TUNNEL THAT THREATENS
by Rukshana Rizwie
The proposed 35 megawatt Broadland Power Station in Polpitiya was
supposed to be commissioned 20 years ago. But the issues that plagued
the power plant then, continue still. Several court cases later, the
plant is still two years behind schedule.
Residents around the proposed site have been up in arms since the
inception of the China-funded Ceylon Electricity Board project. A school
teacher M.A.K.A Gunawardena told the Sunday Observer, of harrowing tales
of homes slipping into sink holes, and the constant barrage of
explosions during rock blasting.
"The problems started when plans for the project changed," he said,
referring to the construction of the 3 km tunnel, initially meant to be
constructed alongside the river. "Contractors were to dig a tunnel along
the Kelani River, but half way through they realized it was not feasible
and moved away.
That's when rock blasting took its toll on the homes uphill. The
result was sinkholes and cracked walls," he said.
Gunawardena said, officers from the Divisional Secretariat and the
National Research Building Organization (NBRO) were quick to warn of the
impending disaster. "Due to the extent of the damage, it was not
possible to live there and when we were warned of the impending
disasters we moved."
Environment Impact Assessment
The US$ 82 million hydro power plant is a run-of-river (ROR) type
with the main dam located near the confluence of the Maskeliya Oya and
Kehelgamu Oya, two main tributaries upstream of the Kelani River.
The main dam and weir would be located in the Ambagamuwa Korale
division of the Nuwara Eliya district, and the powerhouse in Yatiyantota
division in the Kegalle district. It is in the Ambagamuwa division that
residents have been complaining and protesting.
Based on the specifics of the project, a diversion weir will be
erected in Kehelgamu Oya to divert its water to the Maskeliya Oya via a
one km tunnel. The other diversion, which is the main dam of the
project, will be erected in Maskeliya Oya, and the purposal of this is
to divert water from both streams to the powerhouse.
Water from the main dam will be conveyed to the proposed 35MW
powerhouse, first, via a cut-and- cover conduit and then through a 3 Km
tunnel.
The Environment Impact Assessment (EIA) of the project was prepared
by the NBRO and approved by the Central Environment Authority (CEA) in
November, 2006 and extended till February 2010. The EIA states, "there
will be no serious impact on the natural/social environment due to this
project."
Referring to the impact on land use, the EIA cautions that illegal
encroachment during pre-construction stages is to be expected and would
be done with the prime intention of seeking compensation.
On resettlement, the EIA clearly states that 49 families with a
population of around 140 from the dam site and five families with a
population of around 20 will require resettlement to another location.
The existing houses and shops will be demolished with the
construction of the dam, conduit, road and powerhouse.
Most challenging plant
Project Director of the Broadland Power Station Dr Kamal Laksiri told
the Sunday Observer, among all projects he had handled at the CEB, the
Broadland Power Station was proving to be the most challenging.
"When the project was initiated we identified 48 families who would
be directly affected, and asked them how they would like to be
compensated. They wanted an alternative land and money, to which we
agreed. They were paid a minimum of Rs 2.2 million each and the family
with the biggest extent of land received Rs 5.8 million," Dr. Laksiri
said, showing us letters proving that residents had accepted
compensation.
He said, in the construction of the tunnel, the engineers found
ground conditions too weak and unstable. "We would have had to cut down
many slopes and relocate an existing main road," he said. "Several
delays ensued when the forest department refused to allocate land for
the powerhouse downstream since it was taking more space than initially
required."
But the project forged ahead and in 2013 they began rock blasting.
"We are allowed to use explosives in rock blasting the whole day but we
would only do it four times a day and stop by nightfall," he said,
adding that the Geological Survey and Mines Bureau (GSMB) was monitoring
the work.
In April this year, residents petitioned against the plant, citing
that the work was causing inconvenience, and lodged a complaint with the
police.
Enjoining Order
Attorneys-at-law Champika Priyadarshani and Anushka Dharshani
appeared for the complainants. Attorney at law Champika told the Sunday
Observer, residents had complained of severe noise pollution and that
the road works were hampering their day-to-day activities.
Hatton District Judge and Magistrate Prasad Liyanage issued an
Enjoining Order on the Project Director and Chief Engineer of the
Chinese construction company to carry out digging activities without
inconveniencing the public. He also ordered that the project officials
carry out the rock blasting work under the close supervision of the GSMB.
Inconvenience payments
"Residents living within the 100 metre belt were the most affected by
the noise and we reached an agreement with them to provide them an
'inconvenience payment' of Rs.16,000 a month," Dr Laksiri said. The
residents however complained to the Sunday Observer that the payment was
abruptly stopped.
Dr Laksiri explained that last month, residents who signed up for the
payment wanted to change the agreement. "We signed agreements with them
citing that we would stop rock blasting by 9 p.m., but they wanted to
change it to 6 p.m. which we refused," he said. "It was due to this
disagreement that payments were halted until a solution could be
reached," he said.
A discussion was held last week on Monday (22) when the residents
agreed to revert to the old agreement and their payment was made the
following day. It was however not the end of their troubles for the
power plant.
During construction, engineers found unusual ground conditions uphill
where there were cavities with water.
"We used an advanced technology to drill the ground but it turned
into a fountain of water and gas," he said. "Due to the weak ground
condition, two houses began to slip into a sinkhole. We immediately
evacuated four families, compensated, and resettled them."
Resettlement
The NBRO found that 37 families would need to be resettled. "The
first 12 were relocated in the first phase," Dr Laksiri said, showing us
the letters of approval. The second phase is yet to be done he said.
Another resident A. Karunarathne told the Sunday Observer that it was
no longer safe for them to stay. "We have been told that we would be
resettled soon.
When the Minister of Power and Renewable Energy Ranjith
Siyambalapitiya was here two weeks ago, he promised that we would be
resettled within 10 days," he said. "It's been more than 10 days and
we're still here."
River sports, tourism in danger?
According to the International Rafting Federation (IRF), one of the
top 10 endangered rivers which the IRF listed as a hot spot for water
rafting is the Kelani River at Polpitiya. The website says that
construction activities for the proposed Broadland Hydro Power Station
in Polpitiya are a cause for concern. The White Water Rafters'
Association in Sri Lanka continues to protest over the proposed
construction saying that diversion of the river would cause an
indefinite change in the flow and consistency of the water.
Upul Fernando, one of the many operators of white water rafting
expeditions said, the stretch of the Kelani River has 18 rapids of which
13 will diminish when construction is completed. He told the Sunday
Observer that there are many businesses which thrive on income generated
from the water sport that will be affected if the water was diverted.
According to information available online, in 1995, there were only a
handful of licensed operators and well known rest-houses. Today,
Fernando tells us, there are more than 20 operators and more than 15
small scale hotels and rest-houses which cater to both locals and
foreigners.
Dr Kamal Laksiri, project manager of the Broadlands Power Station
conferred that the diversion of water from the river could have an
impact, but said, a solution had been proposed to which tour operators
were yet to respond.
"We discussed the possibility of setting up a mini hydro power plant
which will discharge water back to the Kelani River," he said. "We can
decide on how much water will be needed to be discharged, but we're told
that the operators in the area were not in agreement to this either."
Sources told the Sunday Observer that a group of rafters were
petitioning against the plant and were in the process of filing a case
in court.
(RR) |