CB Governor:
Corruption charges baseless
by Shirajiv SIRIMANE
NDF Presidential Candidate Sarath Fonseka and the combined Opposition
have accused the Government of waste and corruption to the tune of Rs.
430 billion, saying that these funds could instead be used for public
welfare.
 |
Central Bank Governor Ajith Nivard
Cabraal |
They have mentioned the CPC, Mihin Air, SriLankan Airlines,
Kerawalapitiya, Uma Oya, Weerawila Airport project, MiG deal, VAT scam
flyovers and the Hambantota Safari park as examples of institutions and
projects where acts of corruption have allegedly taken place. In a
recent interview, Central Bank Governor Ajith Nivard Cabraal explained
the actual costs associated with these projects and exposed the baseless
charges of the Opposition.
Here are excerpts from the interview:
Q: The Opposition has charged that over the past few years, there has
been a loss to the country amounting to Rs. 430 billion. Fourteen
allegedly corrupt deals of the Government including the hedging deal of
the Ceylon Petroleum Corporation (CPC), Mihin Air, the Kerawalapitiya
Power Plant and the VAT scam, are said to have caused this massive loss.
Let's start with the hedging deal which is said to have caused the
biggest loss, amounting to more than half of the grand total of Rs. 430
billion.
Does the loss from the hedging deal of the Ceylon Petroleum
Corporation amount to Rs. 230 billion?
A: I have studied these allegations of massive corruption and waste
because this is an important issue from the point of view of the
stability of our economy. Over the last two or three years, there have
been many attempts to destabilise our economy. These attempts were made
in various ways, by dissuading investors from investing, by constantly
highlighting a threat of trade concessions being withdrawn, by making
threats of non-repayment of sovereign borrowings, etc. I see the present
attempt also as another such attempt. That is why I have made a special
study of the subject.
With regard to the hedging deal, I do not know how anybody has come
up with the figure of Rs. 230 billion. The total amount that the five
banks have claimed from the Ceylon Petroleum Corporation amounts to US$
418 million. This amounts to about Rs. 47 billion. So, the figure of Rs.
230 billion is a complete fabrication from any angle. At the same time,
even though US$ 413 million has been claimed by the banks, there is
absolutely no reason for the CPC to honour such claims.
In the case of hedging transactions, there are certain norms to
ensure that such transactions are structured in a proper, orderly
manner. In many countries it has been found that certain hedging deals
have not been structured properly. For example, in China, Korea and
India, there have been instances of mis-selling and there was no
liability at all established in relation to claims that were made by
various banks.
In Sri Lanka too, the Central Bank looked into the transactions
entered into by the CPC and the banks, and after a detailed
investigation, we have made a very clear determination that these
transactions have not been structured properly, and that these
transactions are tainted, and accordingly should not be given effect to.
So, there is no money due to be paid by the CPC. But, that is not to
say that the banks cannot make claims. If an accident occurs, claims can
be made from the insurance company, but the insurance company may find
that something is not right, in which case, they are not obliged to make
the payment. In this instance, the Central Bank has determined that the
transactions are tainted, and the CPC is not obliged to pay. So nothing
has been paid as alleged. Neither will any such payment be made.
Certainly not Rs. 230 billion or even Rs 47 billion. Further, I also
know that the Attorney General is defending the CPC in arbitration
proceedings abroad, and he is confident that the country will not have
to pay any money at all.
Q: Let's talk about the cost of arbitration and even the remote
possibility that we may have to pay up.
A: If we have been wrongfully claimed against, we have two choices.
One is to pay up, even though we know it's wrong. Sometimes, this is
done for various reasons. The other option is to defend ourselves
through legal proceedings.
The very fact that payment, in this instance, has been resisted shows
that there is no corruption involved and the CPC is confident of its
position. The cost of arbitration is certainly not going to be billions,
and it is likely that it may be a few millions because it involves
foreign counsel as well.
But, it is certainly better than just paying whatever the banks
claim. Nevertheless, I am somewhat concerned that this figure of Rs. 230
billion is being floated about by certain quarters who are raising this
issue, because someone at some stage may be thinking of making such
payments which is totally out of line with the amount claimed.
Q: Are you saying that if some future government decides to pay up,
there could be some hanky panky in the payment process, like these
allegations of depositors in these failed finance companies paying
executives a good cut if their deposits are returned to them?
A: I wouldn't like to speculate on that, but in this instance, you
will appreciate that someone will resist paying only if that person is
honest and incorrupt, which means that there is no occasion for anyone
to receive any kickbacks for paying up. If someone was in a hurry to
make these payments, allegations could be made.
However, in this case, since no money has been paid, there cannot be
allegations of kickbacks. But, let me reiterate that I am concerned that
an arbitrary amount of Rs. 230 billion is being floated around, which
could be done possibly with a view of such persons making allegations
considering making such a payment at some later date.
SriLankan Airlines
Q: To move on to the next issue, SriLankan Airlines is said to have
suffered a loss of Rs. 10 billion. How did this happen?
A: The global airline industry went through one of the toughest
periods in its history, in 2008. If any airline had made money, it would
be an exceptional case. All airlines including Japan Airlines, Cathay
Pacific, Singapore Airlines and British Airways, made losses.
In fact, Japan Airlines is now on the brink of failure, with its
share price dropping from 356 Yen a few months ago, to just 8 Yen last
week. There were less travellers, so flights had to be cut back. Flights
had lower loads. There were massive increases in fuel charges. The
entire expenditure on fuel could not be recovered from customers. Oil
prices were high in the first part of the year, and there were less
passengers in the second part of the year. So, both these factors had a
heavy impact on all airlines.
 |
No corruption in CPC
hedging deal |
In addition to these global issues, SriLankan Airlines had to face
more challenges. In the latter part of the year, there were less people
travelling to Sri Lanka because the conflict had escalated. Also, the
decline in the number of tourist arrivals due to travel advisories being
issued by certain countries also affected the airline. All these matters
led to the airline suffering losses. However, when the global situation
eases, the profitability of SriLankan Airlines should improve. We are
already seeing signs of improvement.
Q: The budget airline, Mihin Air has been the subject of much
discussion. Has Mihin Air caused a loss of Rs 4 billion to the country?
A: The budget allocation for Mihin Air has been about Rs. 3,300
million, which is a very modest capital for an airline. We have to
understand that Mihin Air is a new airline. The airline and shipping
industries are long gestation businesses.
The moment you get into business, you aren't going to make money. It
was the same with SriLankan Airlines. It takes four or five years before
you start breaking even. Even a grocery business takes a couple of years
to make a profit. In the case of Mihin Air too, there will be a
reasonable gestation period before it turns profitable.
On top of all this, the global downturn in the airline industry
affected the new airline. At the same time, Mihin Air has had a certain
service element too, where it has been the less affluent Sri Lankans who
used this budget airline and went on pilgrimages to Bodh Gaya and Mecca,
as well as for Sri Lankan migrant workers to travel to the Middle East
at a cheaper cost.
Budget airlines make money on volume, but it takes some time to build
up the volume. Because an airline does not make money in the first year,
it should not be deemed a failed enterprise, or as a corrupt
organisation. Over the past few months, however, it should be pointed
out that there has been a reasonable turnaround of the financial
performance of Mihin Air due to business picking up and that has led to
losses decreasing substantially. Needless to say, if these conditions
continue, Mihin Air will turn around soon.
Feasibility study
Q: Did the feasibility study for the Weerawila airport cost Rs 500
million?
A: That is completely untrue. According to the information we have,
Airport and Aviation Services has spent just Rs. nine million (not Rs.
500 million) for the initial work relating to the Weerawila airport.
This included the environmental impact assessment (EIA). In any major
project, an environmental impact assessment has to be done.
Once the EIA was completed, and the location was found to be not
suitable, the project was shifted to Mattala. There is nothing untoward
in this. A location has to be studied to determine whether it is
suitable for such a project. Anyway, from what I gather, some of these
approvals had been granted when Mangala Samaraweera was the Minister of
Aviation.
Q: MIG deal?
A: There is absolutely no truth in this matter too. The Defence
Secretary has already filed action against the newspaper which stated
that there was corruption in these deals, and the matter is now in
Court. If there was corruption as stated, why should the Secretary of
Defence take the newspaper to Court?
Q: There is an allegation that during the period that President Mahinda Rajapaksa functioned as the Minister of Finance, there was a VAT
fraud amounting to Rs. 35 billion.
A: According to the audit report, this fraud happened during the
period between November 2002 and December 2004. So this certainly is
before Mahinda Rajapaksa became the President and Finance Minister. In
fact, this fraud was unearthed after President Rajapaksa became the
Minister of Finance and now there are court cases pending on this
matter. Action has been filed against those involved. In any case, the
amount involved is not Rs. 35 billion but Rs. 3.5 billion. I don't
understand how these figures are just plucked out of the sky.
Q: There is also the allegation that Rs 1.6 billion is being spent on
setting up a safari park in Hambantota when the Yala Wildlife Sanctuary
is close by.
A: From what I have learnt, this capital expenditure is not for a
wildlife reserve, but for a theme park which will feature animals like
lions and zebras which are not found in the wild here. This is a
different concept, a sort of cross between a zoo and a wildlife
sanctuary. This concept is seen in other countries too. Attractions of
this nature are needed if Sri Lanka is to be promoted effectively as a
major tourist destination. Investments of this nature are quite common
in countries which are targeting large numbers of tourists, with a
variety of attractions, and it is good that Sri Lanka too is on this
track.
Q: Was the cost of the Kerawalapitiya power plant inflated to US $
400 million when the actual cost was US $ 200 million?
A: Certainly not. The cost of the Kerawalapitiya power plant was
originally estimated, in 2002, as US$ 390 million. However, due to
careful planning and execution, the cost of the complete project is now
estimated to be only about US$ 295 million, for the power plant of 300
megawatts. That works out to roughly about a million US dollars per
megawatt. That is satisfactory as it is the current industry norm of
about one million dollars per megawatt for petroleum-based thermal power
plants.
Q: Was the capacity of the plant reduced to 200 megawatts from 300
megawatts?
A: Once again, no. The Kerawalapitiya plant is a combined power cycle
plant. The first 200 megawatts is generated with furnace oil.
The exhaust from the first phase is to be converted into steam to
generate another 100 megawatts. The first phase is already in operation
and the second phase will be operational soon, in a matter of a few
days. The cost of setting up this plant will thus be distributed over
the entire 300 megawatts.
Q: The agreed price for electricity per unit from the Kerawalapitiya
plant is said to be Rs 18. But is power now being purchased at Rs 40,
incurring a loss of Rs 22 per unit?
A: The pricing of electricity is done on a predetermined formula
which includes the price of furnace oil. Therefore, no one can set a
specific price which would stand forever, since the price of furnace oil
changes regularly. At current fuel oil prices, the unit cost, although
higher when only the first phase of the plant is operational, will
decline to around Rs. 14/Rs 16 per unit, when Phase 2 of the
Kerawalapitiya power plant is in operation. Hence, this contention is
invalid.
I must also mention that the Kerawalapitiya power plant is owned by
West Coast Power Ltd of which 56 per cent is held by the Government, 10
percent by LECO, 24 percent by EPF and 4 percent by Lakdanavi Co. So,
you can see that almost the entire plant is owned by Government or State
institutions.
Q: There are allegations regarding the Uma Oya project. Did the
estimated cost of this project increase from US $ 265 million to US $
539 million?
A: The structure of a project can change from time to time based on
the project components. There may be add-ons by the time a project is finalised, and it may even have certain components that are dropped by
that time. The original project had an irrigation as well as power
generation component and the estimate of the project amounted to US $
265 million based on input prices in 1999.
The Uma Oya project at that time was meant to produce 50 megawatts of
hydropower and irrigate around 5,000 acres of paddy land. Later, the
project scope was expanded and the hydropower generation capacity was
increased to 120 megawatts and the irrigation scope to 12,500 acres of
paddy. As a result of these add-ons, the project cost was re-estimated
at US $ 545 million in 2009.
It is generally estimated that the capital cost to produce one
megawatt of hydroelectricity is about US $ 3 million. In fact, for the
Upper Kotmale project which aims to produce 150 megawatts, the project
cost is US$ 460 million.
When all these factors are taken into account, the increase in the
project cost of Uma Oya is reasonable and there is ample justification
for the increased.
Q: Was the contract for the Uma Oya project awarded to an Iranian
company without calling for tenders?
A: The financing for the Uma Oya project comes from the Export
Development Bank of Iran. Usually, the agreement in such cases is that
the contract has to be handed over to a company from the country
providing the financing. For example, India will not finance a project
for which construction will be carried out by a company from Australia,
or vice-versa. Similarly, when Iran provides the money, they will want
their corporations to handle the construction.
Even in the past, under the Mahaweli development and other schemes,
the contracts had been given to contractors from the country which
provided finances for the project.
Accordingly, the general practice under bilateral loan agreements is
that construction contracts are awarded to a Contractor of the lending
country, has been followed here too. However, having identified the
contractor, the Government has taken measures to ensure the project is
cost-effective. In fact, the Government has been able to negotiate and
enter into the contract at a lower price than the estimated value. At
the same time, any unexpected costs and adverse movement in prices will
have to be borne by the contractor and no additional payments need to be
met by the Government.
A9 road
Q: Was the reconstruction of the Anuradhapura-Jaffna A9 road handed
over to a Chinese firm at the rate of Rs. 125 million per kilometre? Has
this Chinese company subcontracted the same work to two Sri Lankan
companies at the rate of Rs. 60 million per kilometre? The same
allegation is made regarding the reconstruction of the Point Pedro -
Kankesanturai Road, the Mannar - Pooneryn Road, and the Nandikulam-
Mannar Road.
A: The Road Development Authority had made a proposal for the
rehabilitation of the A9 road and later the project was handed over to
the Ministry of Reconstruction and Rehabilitation. This is an urgent
project and it was essential that it is undertaken as soon as possible.
So, the Exim Bank of China, which came forward to offer the funding, has
been given the opportunity to do so.
 |
SriLankan Airlines is
already showing signs of improvement |
The contractor has agreed to finalise this 153 km project at a cost
of Rs. 15,300 million. Therefore, the expected cost per km is around Rs.
100 million and not Rs. 125 million. However, for contingencies, 25
percent have been allocated. The rates at which the contractor
subcontracts to other subcontractors is not relevant since it is the
original contractor who is finally responsible for the quality and the
delivery of the work. This is normal. For example, in the Mahaweli
project, Balfour Beatty was the main contractor for the Victoria dam,
and they in turn employed various other parties as subcontractors. But,
they were finally responsible for the project.
In the case of the A9 road, it must also be noted that the materials
for construction of projects, skilled labour were not easily available
as this area is now open after 30 years of hostilities. Further,
infrastructure like electricity, water and facilities for engineers are
not easily available for the use of the A9 project, and have to be
supplied by the contractor at a high cost. Such costs naturally have to
be borne by the project.
The cost incurred on the Kandy - Mahiyangana Road was Rs. 117.65
million per km and it was Rs. 98.49 million per km for the Nuwara Eliya
- Badulla project. However, costs differ from one area to another due to
the availability of construction material, terrain, etc.
Q: There is another allegation concerning the purchase of 35 SZPMC
cranes for the Colombo port. The original cost of each crane is supposed
to be US$ 600,000. Has the price been inflated to US$ 1.2 million each?
A: That is quite different to the figures I have. Thirty transfer
cranes with a capacity of 50 tonnes each was purchased by the Ports
Authority at US$ 1,507,000 each. Twenty five years ago, in 1985, they
had got 35 tonne transfer cranes at US$ 1,570,000 each. So, a quarter of
a century later, they have bought transfer cranes at US$ 63,000 less,
and that too with an increased capacity of 15 tonnes.
Q: Was the price at any stage US$ 600,000 per crane?
A: If the cost of a crane was US $ 1.57 million in 1985, it couldn't
have been US$ 600,000 in 2009.
Flyovers
Q: Then we come to the four flyovers. The costs that are said to have
been incurred are as Rs. 2000 million for the Kelaniya flyover, Rs. 1200
million for the Nugegoda flyover, Rs. 900 million for Dehiwala, Rs. 1000
million for Orugodawatte - all this is said to be when the international
price for such a flyover was Rs. 400 million.
A: It is very silly to say that a flyover will cost the same
everywhere. The number of lanes, the terrain, the barricades, the
surface, and many other factors could be different. The actual costs
incurred in these projects are also different to what has been stated by
you. The Kelaniya flyover cost Rs. 1700 million, Nugegoda Rs. 800
million, Dehiwala Rs. 960 million and Orugodawatte Rs. 650 million. It
must also be noted that those are flyovers with steel structures.
Certainly, building a concrete flyover will cost less than a steel
structure. However, steel was opted for because the roads cannot be kept
closed for too long and the construction has to be completed in two or
three months. A concrete structure takes a longer period of time to
construct.
Q: There is said to have been a US$ 16 million contract to supply
computers to Divisional Secretariats. The computers supplied are said to
be locally assembled machines with no brand name and most are said to be
out of order and unusable now.
A: This question relates to the Lanka Government Network (LGN)
project which was funded by the Korean Government. Under this project,
325 Government organisations were connected to the LGN. The contract
value of the project was US$ 14.5 million. The value of the computer
equipment (computers, monitors and keyboards) was US$ 2.3 million. The
balance US$ 12.2 million was for licensing software, network equipment,
servers, LGN hub, setting up of data centre equipment and the cost of
broadband connectivity for three years for 325 locations, where 3,235
computers have been installed.
The computers are of a Korean brand and here too, only Korean
manufactured computers have been allowed under the aid conditions. They
are not locally assembled machines as reported. Also, as of now, 3,223
computers are in proper working condition. I am also told that 12
computers are presently under repair and are being fixed under a
three-year warranty and maintenance which is also included in the
contract.
Q: Rs. 430 billion is said to be the cost of all this alleged
corruption and waste. The hope held out on the political platforms was
that by recovering this amount, wages could be increased, pensions could
be increased, Golden Key depositors be repaid, and various other things
done with this money.
A: Such calculations amount to a scam. This is non-existent money.
For example, the figure of Rs. 230 billion that you mentioned in
relation to the hedging deal does not exist.
No such amount has been paid or is due to be paid or has even been
claimed by any party, so it cannot be 'recovered' for wage increases or
any other payment or liability. This type of logic can only be described
as fanciful daydreaming, or incredible foolishness or downright
dishonesty.
|