Lotus Tower project:
Political interference in lift contract - TRC
More skulduggery of the former regime under the pretext of
development has come to light with the cost of the Lotus Tower project
on D.R. Wijewardene Mawatha exceeding the initial investment due to the
delay and haphazard planning and implementation of the mega sky rise
complex.
Sources at the Telecommunications Regulatory Commission (TRC), for
which the tower is being built, said that the cost of the project will
increase by over US$ one million as a result of the delay caused by the
consultants in finalising the contracts for the construction of the
lifts and escalators. The construction of the Lotus Tower which
symbolises purity was due to be completed by June this year. However,
due to the delay in finalising agreements with subcontractors for the
manufacture and supply of lifts the timeframe was extended to October
2017 by the new Board of the TRC.

An artist’s impression of the Lotus Tower |
The new Board is headed by P.B. Abeykoon and Director General M.M.
Zuhair.
“The new management is reviewing the construction and supply of lifts
and escalators and steps will be taken to continue work on the project
in a transparent and professional manner. There was absolutely no
professionalism and transparency in the planning and implementation of
the project by the former management,” he said.
He said the new management will be compelled to extend the time for
the completion of the project following the request of the Chinese
contractors. The request for extension is under consideration. Work on
the project which was launched in late 2012. It took over one-and-a-half
years since August 2013 to finalise the contracts for the construction
of lifts and escalators.
The process of finalising the contract had been going on till January
this year.
“Specifications should have been done at the beginning of the project
to meet standards. There was total negligence by the consultants. As a
result, the lifts had to be fitted to the constructed structure. The
lift manufacturers agreed to construct it according to the built
structure. Consultants of the University of Moratuwa and the Chinese
constructors went ahead with the task according to schedule,” sources
said. However, there was a major flaw in finalising the contracts for
lifts and escalators. It should have been finalised at least by early
2013 but till October 2014 the consultants had been unable to decide to
whom the subcontract should be awarded to.
Subcontractors were decided only by October 2014. The former Board
approved the selection of subcontractors for the lifts and informed the
contractors to go a head. The documents were signed by five
professionals of the University of Moratuwa which included two
engineers. Suddenly the award of the subcontract changed in November
2014 with the approach of the Presidential elections in January 2015.
- LF
|