Eco-impact warning: Coal imports under fire
Tender procedure questioned:
By Rukshana Rizwie
Startling revelations have surfaced in a study by an independent
committee appointed to probe the procurement of coal for the Lak Vijaya
Coal Power plant indicating that there had been complete disregard for
environmental impacts and arbitrary change of technical specification
during the bidding process. The experts committee has recommended to
Government that the future supply of coal be undertaken through a fully
revised procedure and framework.
The
Sunday Observer is in receipt of the 25-page dossier which details that
the Government of Sri Lanka profited from the coal tender with a gain of
USD 7,596,676. However, it had been achieved at the cost of grave
environmental repercussions arising from the purchase of undersized coal
particles.
The report which was presented to parliament on August 10 was
prepared by an independent three-member committee comprising eminent
academics, namely, Prof. K.K.Y.W. Perera, Prof. Lakshman R Watawala and
Prof Janaka B Ekanayaka who were given 21 days to file a report on
whether the government profited or incurred a loss from the
controversial coal tender in 2015 and 2016. Secretary to the Ministry of
Power and Renewable Energy Dr. Suren Batagoda, told the Sunday Observer
that the document was tabled before Cabinet for deliberations.
Loss
According to the Report , the procurement of coal for two years (2015
& 2016) was split into two: 50% was to be purchased by a long term
tender, while the remaining 50% by spot tender. Until April 5 this year,
four spot tenders were awarded for the purchase of 1,126,805 metric tons
of coal at a price of USD 49.7 per metric ton. Under the long term
tender 1,064,724 metric tons of coal was purchased for a price of USD
57,932,356 at a price of USD 54.4 per metric ton.
Their findings showed that the government profited from the spot
tender purchase with a gain of USD 7.5 million by April 5, 2016.
Since coal had been purchased based on the Newcastle index, there had
been a global downward trend in prices with fluctuations from an index
price of USD 120 in 2010 to USD 65 in May this year, adding to the
profit margin.
Bidders' battle
According to the Report, two bidders, namely, Nobel Resources
International and Swiss Singapore were chosen, of which Swiss Singapore
quoted a bid of US 68.72. It was at this point that the decision was
reached to not consider the grain size when evaluating the tender and
purchasing coal, a decision which would have serious repercussions as
the documents show.
The original price quoted by Swiss Singapore was negotiated and
reduced to US 58 subsequently. Another deciding factor was the change of
index. When bids were called, coal prices were evaluated based on the
Newcastle index, however when it was initiated, the index was changed to
AP14, a South African Index while a penalty on the grain size was also
withdrawn, the Report said.
Bid parameters
The change of two parameters, the physical properties and the coal
index paved the way for Swiss Singapore to reconsider prices, the Report
said. Accordingly, Nobel Resources was to supply coal that did not have
grain size above 50 mm and only 10% of the stock was going to be grain
size below 2 mm. However, Swiss Singapore was to supply 3% of its coal
with grain size above 50 mm and 25% which is 1/4 of the total stock with
grain size below 2 mm, giving it dust-like properties.
It must also be noted that the coal supplied had to be of a Gross
Calorific Value of 6,300 Kcal/kg. Energy experts told the Sunday
Observer that to have a low calorific value means more coal has to be
burnt to generate a given amount of heat and more pollution generated.
The original EIA report prepared in 1999, had stated that only coal
with a calorific value of 63. kcal/kg, sulphur content below 0.7% and
ash content of 11% will be used. If there are any deviations in these
specifications, the plant needs more coal, emit larger amounts of fly
ash and bottom ash and higher amounts of SO2. However, according to the
specifications abided, there was a total moisture of 12%, ash content,
11%, volatile matter, 27% and sulphur content of 0.5% in both bids.
According to the Report, the size of coal plays a minor role in
relation to the plant efficiency. If, however, coal particles are too
large, a separate crusher is used to crush and reduce the size before
being sent to the pulverizer, which needs additional energy and
wear-and-tear of the crusher. However, if the coal size is too small or
less than 2mm, which was the case with coal supplied by Swiss Singapore
where 25% of the shipment were small, the coal particles behave like
dust.
"When stocked in the coal yard, wind will cause the dust to blow and
settle on nearby trees, plants and homes. The probability of
self-ignition resulting in fires while in storage may increase partly
because of high air contact surrounding small particles," the Report
cautioned, adding that the powdery coal dust will have adverse
environmental impacts.
The Report also stated that the Lak Vijaya Power Plant in Sri Lanka
has a peculiar situation which has to be catered to, since coal can be
unloaded only between September and April when weather conditions are
not adverse. At the same time, adequate stocks have to be maintained
approximately for six months to cater to the adverse weather season when
coal cannot be unloaded.
"Therefore, coal stocks and exposed yard are very large thus
increasing the environment damage. Under these circumstances,
controlling the quantity of small and fine sized particles is
desirable."
The Report recommends that a study be undertaken to modify
specifications/penalties to overcome these adverse implications for the
future supply of coal.
[Three-member committee report: Conclusions ]
The country profited from the spot tenders, a total saving of USD
7,596,676 compared to coal purchased on long term tenders.
Without completely relying on spot tenders, a mix of procurement
through long term as well as spot tenders were implemented. This, they
say was good from the point of view of source diversity and supply
security.
A balance between the long term and spot procurement should be
maintained due to changes in market conditions.
It is important to introduce future technical specifications clauses
to penalize oversize and undersize coal after carrying out a detailed
study of their impact to the environment as well as additional cost of
crushing larger particles.
Compared to the original bid price with size penalty, the negotiated
price resulted in a net saving of USD 287,029.
Even if we consider the long term contract and apply the penalty for
size, the majority of shipments have been a financial gain.
Since the payment price for coal is based on the index at the time of
shipment and because the shipment may come from different countries such
as Indonesia, South Africa, Australia, Russia, it is suggested that a
composite index be considered. |