Do not deny or delay the missing link
Congestion at Borella junction through Baseline Road:
by Dr. G. L. Asoka J. de Silva
Having read numerous concerns penned by Dr. Thilak Fernando, Dr.
Hector Perera and Mr. Sunil Thenabadu on the prevailing traffic
congestion at Borella junction, I believe it is my prime duty to divulge
some encouraging, may be yet optimistic, inside information as the
former Director, Engineering Services of Road Development Authority
(RDA), under whose purview the planning, formulation and designing of
the Baseline Project was, until retirement from service in mid April
2007. Now I am able to express and forecast my views more freely.
Dematagoda - Baseline Road flyover under construction in the ’90s |
At the outset I wish to convey my deep appreciation of Dr. Hector
Perera's attitude of accepting reality and also being optimistically
hopeful, expressed in his letter dated 3rd May 2007.
He mentions about a three-lane duel carriageways from Narahenpita to
airport being beyond imagination and impossible 15 years ago and how an
impossible became a reality at Dematagoda railway crossing with the new
flyover.
This reminds me how true it was with real anxious moments I had 37
years back on my way to Katunayake airport, first, being caught at then
narrow gauge level crossing, then at Dematagoda main level crossing and
finally the agony of moving at almost crawling speed along highly
trafficked then sub standard narrow two-lane Negombo road to reach the
airport just to be a bit late.
The current situation may not be perfect but thousand times better
and definitely things would be very much better in time to come within
the next five years or so, if and only if the top most decision makers
are genuinely interested in developing the country as they preach.
Safety
To start with, it is absolutely necessary to have a very clear idea
of the basic primary purpose of the Baseline Project as a whole and the
envisaged objectives and benefits.
If I may briefly out line: it has been identified and designed to
provide a north-south link to ensure the mobility of urban traffic at
reasonable speeds with reduced interference in traversing through
several major and arterial trunk routes with signal controlled
intersections in the Colombo Metropolitan area and the suburbs.
It is not an access controlled highway and is designed to capture
traffic from roads on either side of the project road and thereby
relieve the congestion of traffic on these roads in the surrounding
areas.
Thus, the Baseline Road is designed to carry a substantially huge
volume of traffic while ensuring safety of all the road users including
the pedestrians. It is really considered as the "Inner Circular" road to
the City of Colombo.
Coming back to the topic of prevailing traffic congestion at number
of signal-controlled intersections on Baseline Road, the congestion is
experienced not only at Borella junction though concerns have been
expressed only about Borella junction.
The engineers in RDA have not been ignorant to the heavy and
unprecedented vehicular traffic growth in the future as stated by Sunil
Thenabadu, but had to be contended within certain limitations to make
"the project" financially and economically viable to the satisfaction of
the donor agency.
It is hard to negotiate when being labelled as a third world
developing country as Dr. Hector Perera has quoted. So what the
engineers in the RDA opted was for phased out development, what is
really coming through now.
The sweet news that I wish to disclose now is that we would be having
two major flyovers constructed over and along Baseline Road, one
starting from opposite to Kanatte cemetery and ending up around MRI near
Lady Ridgeway Hospital to fly across three junctions namely; Kanatte, D.
S. Senanayake and Borella.
The other would be to fly across State Road and Orugodawatta
junction. Both flyovers would be four lane width to provide divided two
lane duel carriage ways for the through traffic across the referred
junctions along Baseline Road with two service roads at the grade level
on either side of the ramps for the turning traffic.
Unlike in a flyover bridge across an isolated junction, in these
flyovers, in between the ramps at the two ends, the turning traffic on
the at grade level would be moving right under the flyover decks on
multiple lanes in both directions, with these flyovers being constructed
on single centre columns.
Each flyover would be about 1.5 to 2.5 km in length. The present
signal controlled intersections would be maintained at each junction
under the flyovers for the turning traffic.
Therefore additional acquisition would be required only at the ramp
areas just like in Dematagoda flyover across the main railway lines
where six lanes have been provided for the through traffic across the
level crossing. Due to mixed traffic at these junctions, it has been
estimated that four elevated lanes would be sufficient for the through
traffic across these junctions.
It has also been decided that present raised foot walks would be
continued right along Baseline Road for the convenience of the
pedestrians. We are confident that this proposal would get materialised
unless the top decision makers who talk so much on the importance of
development of infrastructure as the basic pre-requisite for the
sustainable economic development of the country get cold feet and decide
otherwise in favour of few who may get affected.
I frankly do not think funds would be a stumbling block as the
Japanese Government agencies like JICA and JBIC are very much keen in
upgrading the project they have funded to maintain a meaningful level of
service.
Reality
Dr. Perera mentioned in his letter on the pedestrian underpass at
Borella Junction, which he quoted as "was not thinkable a few years ago
but has become a reality". I must confess that this underpass was not an
item in the original BOQ but was introduced as a result of a collective
decision taken at the then coordinating committee meetings RDA used to
have under the chairmanship of the Secretary to the Ministry amongst all
the stake holders such as CMC, Police, UDA, utility agencies, SLLR & DC,
CGR etc.
Although it had to be included under a variation order at a slightly
high cost, it is fully worth as could be seen.
It also maybe of some interest to know that at an evening discussion
session held at the Institute of Engineers of Sri Lanka to assess
various aspects of the Baseline Project, few very senior engineers
including a very eminent engineer who is deceased now, were very
critical and were of the view that Baseline Road has been extravagantly
planned to provide six lanes and would be a white elephant as there
would be many empty lanes due to lack of traffic.
RDA had to defend solidly to convince them that situation 25 years
ahead has been considered and that there is a possibility of even
reaching a much lower level of service then than anticipated.
Chock-a-block
It is also important to note that there is clear evidence of being
able to realise one of the main objectives of the Baseline Road Project
even after completion of the present two phases of the project up to
Kirulapone junction on High Level road since the traffic congestion on
the previously chock-a-blocked main roads though Maradana, Borella and
Panchikawatta has eased out to a very great extent.
This is as a result of the Baseline Road catering to six lanes
divided traffic is being able to carry a huge volume of vehicles. It may
be worth noting that the present traffic volume on the Baseline Road is
of the order of 80,000 vehicles per day (VPD) at Orugodawatta State Road
area, 69,000 VPD at Borella, 62,000 VPD at Kanatte junction, 57,000 VPD
at Narahenpita and 42,000 VPD at Kirulapone.
Now we come to the pathetic situation in the Phased III section of
the Baseline Project. To realise the envisaged economic benefits,
completion of Phase III is absolutely necessary. However, RDA has been
struggling to achieve this for the past decade or so against many odds.
From latter part of 1994, RDA has finalised the alignment for the
selected trace and had reserved a corridor of 150 feet wide to prevent
further improvements and new developments within it, with the two local
authorities concerned namely, CMC and Dehiwala Mount Lavinia MC.
At one time, RDA was severely criticized for not conducting an
Environment Impact Assessment (EIA) study for this completely new 7.5 km
long southward extension from Kirulapone to Maliban Junction. (This was
due to a conflicting clause in the Central Environment Authority (CEA)
regulations for constructing a highway less than 10 km) and RDA
subsequently honoured an undertaking given to the courts on fundamental
right cases filed to have a complete EIA study conducted and EIA
approval has been obtained from the CEA as required.
But, RDA has not been able to commence construction work on Phase III
from Kirulapone to Maliban junction, which would invariably benefit
millions of the general public, due to the protest of few die-hards
amongst the affected parties. Like in any other development projects
acquisition of properties, demolition of buildings and houses cannot be
avoided here too.
What is getting affected is a mixture of single and two storied
houses both old and new, fair amount of shanties, bare lands etc.
RDA has offered a very handsome compensations package equivalent to
the compensation packages adopted for all the other major development
projects such as Southern Expressway, Outer Circular Highway, Katunayake
Expressway etc. to everyone of the affected persons.
(To be continued next week)
The author was Director Engineering Services, Road Development
Authority, now resident in Calgary, Canada.
|