Floods and obsolete warning system
By Justice P. H. K. Kulatilaka
A flood is defined as a body of water that rises to overflow into
land settlements which are not normally under water. When there is heavy
rainfall in the catchment areas it is natural that flood situation will
arise. Floods invariably create problems of a serious nature. Hence it
is considered a natural disaster.
Riverine floods develop slowly when there is rainfall for a
continuous period, especially during monsoons. It may come in the form
of a flash floods with excessive rainfall falling within a period of
time duration. This happens when a tropical cyclone or a depression
strikes. Flooding can also occur from a dam breach episode producing
effects similar to a flash flood. The flood effect can be of a local
impact in the neighbourhood or community or it can be very large or it
could be floods affecting a large area of the river basin.
Riverine floods
Sri Lanka is blessed with 103 rivers. Of these 17 rivers are
associated with flood problems. These 17 rivers have a catchments area
of about 1,600 square kilometres. It is a known fact that with the
population explosion since independence, land area has become scarce and
as a result low income families were forced to occupy flood plains of
rivers which have been demarcated as reservations. A case in point is
the unprotected areas between the bunds in the Kelani basin where people
are now living. When the water level reaches, 5 feet mean sea level (msl)
some of these areas within the unprotected area in the Kelani basin get
submerged, when flood water rises up to 7 feet msl. all unprotected
areas go under water. Flood situations would arise due to unscrupulous
actions of man. Putting up structures and land use without considering
flood risks have often invited flood situations.
"Uncontrolled/unplanned" land use in the Kelani Ganga catchment area is
an example. It has posed problems in carrying out dynamic flood control
plans.
Floods of Kelani Ganga
In the year 1925, the British who were the rulers then, realised the
danger of floods and built two flood bunds for protection of the
surrounding area of the two banks of Kelani Ganga from floods. Since
then floods in 1930 reached a level of 10.9 feet msl. The bunds
overtopped and breached. In 1940 floods reached a level of 11.06 feet
msl. Since the duration of the flood was short the bunds did not breach
but during the floods of 1947, flood level reached 12.05 feet msl, and
the bunds overtopped. The experts warn that if the flood level of Kelani
Ganga reaches 13 feet msl, the floods would inundate areas right upto
Thimbirigasyaya.
Mechanism
The measuring of flood level is being done at the Nagalagam Street
Gauge. When the water level rises to 4 feet msl, the river is at minor
flood level, when it reaches 7 feet msl, river is at major flood level
and when it reaches 9 feet msl, river is at critical flood level.
Upper reaches of Kelani Ganga is steep, hence it is unlikely that the
river overflows its banks. From Hanwella the river flows through flat
land. Therefore, the first flood waves start from Hanwella. For this
purpose a flood gauge has been installed at Hanwella. Readings at
Hanwella gauge would enable the head office to predict the flood level
to which the river would rise at Nagalagam Street. Information from
Hanwella comes to the head office through a telephone dial-up link.
Height of the water level is measured through visual observations.
This is highly unsatisfactory. If modern automated gauges are installed
data will instantly be transmitted to the head office, which would
enable the head office to monitor for the process of potentiality of
flood situation and inform people early.
Apart from the Flood Monitoring Station at Hanwella there are
stations at Deraniyagala, Kitulgala and Olonboowa. The data is
transmitted through radio transmitters. Engineers in the Irrigation
Department underscore the need to have automated gauges and other modern
instruments in order to carry out its functions effectively.
The flood office at Nagalagam Street is manned 24 hours. The water
level of the river is recorded hourly and the office has a telephone
link with the head office.
There is a system of flood committees which come into operation with
the recording of flood situation. When the Nagalagam Gauge records flood
level of 4 feet msl, the Flood Committee comes into operation. It is
chaired by a regional irrigation officer. The Divisional Secretary is
also involved in this committee. When the flood level reaches 6 feet msl
a flood Committee which will be chaired by the Director General of
Department of Irrigation comes into operation. At this level,
Superintendent of Police, Divisional Secretaries are also involved. When
the flood level reaches 9 feet msl, Government Agent's Committee takes
charge. This committee includes, apart from the officers of the
Irrigation Department, Police and Navy personnel as well.
There are Standing Orders coming into operation during flood
situations.
When the aforesaid mechanism is in operation, in case of minor
floods, warning is given 12 hours ahead. In the case of major flood (7
feet msl) warning is given 18 hours ahead and in the case of critical
flood level, warning is given 30 hours ahead to the people.
Anyway, there is a possibility of bund breaching when the river
reaches major flood level but before it reaches the critical level. In
order to avoid a calamity, continuous patrolling of the bunds is done by
the Irrigation Department officials.
The need to have a proper inundation mapping project is badly felt.
Inundation mapping helps to demarcate the flood prone areas and also
identify the safety zone where people can be evacuated during flood
situations.
Modern equipment
The present equipment installed at the Nagalagam Gauge station and
the Hanwella Gauge station need upgrading with installation of modern
equipment such as automated rain gauges so that real time data relating
to arrival time of flood waves could be accurately ascertained.
In order to measure the rainfall in catchment areas and its intensity
automated rain gauges have to be installed in the catchment areas. Then
the head office in Colombo would be able to provide real time data in
making proper assessment and give warnings to the people.
Kaluganga Basin
Floods in Ratnapura are more or less annual phenomenon. Kaluganga
catchment are a receives the heaviest rainfall during the South West
Monsoon period. Kalu Ganga in its upper reaches flows through a fairly
steep slope and as it flows down, the speed and the volume of water
increase.
The reaches of the river beyond Ratnapura are at a low gradient and
hence the river flows at a slow speed. The volume of water gushing down
the upper reaches of the river cannot immediately be accommodated by the
middle reaches of the river that flow down slowly beyond Ratnapura, this
resulting a flood situation submerging Ratnapura town.
As far back as 1960 there had been a proposal made by an engineering
firm commissioned by the Sri Lankan government relating to flood control
plan on Kaluganga. This did not see the light a day.
Apart from the geomorphologic factors referred to above, there
appears to be certain human factors that accelerated flood situations in
Ratnapura, namely, cutting into the banks of streams around Ratnapura
for sand mining. It appears that the ulterior motive is mining for
gemming. In this process heavy equipments like backhoes are being used
to dig the river banks. These unscrupulous and uncontrolled digging lead
to landslides as well.
Till very recently the licences for gemming and sand mining were
issued by the Geological Survey & Mines Bureau (GSMB) with the approval
of the Divisional Secretary. Now the GSMB directly issues licences.
Approval of the Divisional Secretary is not a requirement. As a result,
licences are being given to dig streams and banks which are not at all
suitable for mining.
Therefore, in issuing licences for gemming and sand mining, the
authorities, will have to be very cautious and the approval of the
Divisional Secretaries who have first-hand knowledge of the area should
be made a prerequisite in issuing such licences.
Apparently a disaster preparedness plan has been evolved by the
Divisional Secretariat. Steps have been taken to increase effectiveness
of emergency services with the assistance of the Irrigation Department,
Police and the Navy and to implement people's awareness programs. There
is a special unit in the Navy to assist the Government Agent, Ratnapura
during flood situation.
Dam-breaching
Serious consequences could arise out of dam breaching. A case in
point is the disaster brought about by Kantale Reservoir Dam failure in
1986. There was heavy loss of life, 68 dead bodies were recovered and 59
people went missing, 592 houses were completely destroyed, 628 houses
were partly damaged, 2035 families were displaced and 2500 acres of
planted paddy were destroyed. Kantale dam was an ancient dam built in
the 7th century and its sluice gates have been constructed out of stone
masonry and clay mortar. In this episode there was no prior observation
of signs of warning.
Dangerous consequences that would result in the event of a major dam
breach were highlighted by a rough inundation mapping conducted by a
joint committee representing the Irrigation Department and the Mahaweli
Authority in respect of Kotmale Reservoir Dam.
It appears that if the dam breaches flood waters will inundate the
entire Kotmale town, part of Kandy town and Peradeniya.
The Irrigation Department has 315 major projects. Of them 54 are
large dam category projects. An inspection and assessment done by the
World Bank Project in 2003 had assessed 34 major dams and identified
them as having some risk factors.
Some of these dams are "ageing" and as such a vulnerability
assessment of each of the major dams need to be undertaken.
The factors that are responsible for dam-breaching are enumerated as
follows:
i. Overtopping due to flood situations caused by heavy rainfall.
ii. Foundation failure. Even though when a hole is drilled at 100
meter intervals on the dam and if weak soil is found it is treated by
injecting grout (a mixture of cement and water) there still can be weak
spots through which seepage could take place leading to collapsing of
the dam.
iii. Slope failure in the upstream side. This may result due to rapid
lowering down of the water level to stop overtopping. It would lead to
landslides in the upper stream region.
iv. Slope failure in the downstream due to seepage. Downstream slope
will get saturated and slide down.
v. Erosion e.g. Kantale Reservoir Dam referred to above.
It is interesting to note that these inspections are based on visual
observations.
If dam danger signs (i.e. weak spots) are detected drilling is done
and injected with grout, and in some cases water level in the reservoir
is brought down. If there is a danger of overtopping, the divisional
officer will immediately inform the regional office. For that purpose
they are supplied with residence telephone facilities and there are
Standing Orders to cover up such situations.
The Irrigation Department is equipped with the expertise, they have
275 Engineers. When the reports come to Head Office the Dam Safety Unit
which is chaired by the Deputy Director and a few Engineers study the
repot and if the Director's intervention is necessary for the matter, it
is referred to the Director himself. The annual budget for dam safety is
around Rs. 15 million.
Unfortunately there is no mechanism to give early warning to people
even if a dam breaches, what the Department does is to get the
assistance of the Police, Army and with loud speakers mounted on
vehicles tell the people.
Kantale Tank Dam episode is a case in point.
This kind of situation is highly unsatisfactory. Therefore in case of
dam breach situation the Irrigation Department has no mechanism in place
to give prior warning to people.
Suggested preventive steps
i. Install micro-seismometers at the dam sites which should be
connected to Peradeniya Seismic Network.
ii. Install altimeters, strain gauges, piezometers whereby pressure
builds up and seepage could be observed. It is heartening to note that
the Irrigation Department is making negotiations with the World Bank in
this regard.
iii. Implement and Inundation Mapping project. This could be
undertaken by the Survey Department. If Inundation maps are available
the flood prone areas in the event of a dam breach and the level to
which flood water would reach can be ascertained. At the same time high
level areas to which people could be evacuated or can go for safety also
can be identified.
iv. Have all instrumentation necessary for testing the stability of
soil in the dam site.
v. Undertake vulnerability assessment of each of the major dams that
pose hazards.
vi. Set up Flood Watch so that warnings could be issued to the people
in advance of possible dam break. This would help to reduce the
casualties and death toll in a flash flood.
vii. Conduct awareness programmes for the people.
The writer who is an honours graduate in Geography is the Deputy
Director Sri Lanka Judges' Institute, a member of the Tsunami Commission
which inquired into natural disasters in Sri Lanka and a former judge of
the Court of Appeal. |