Construction work on Kataragama- Matara rail track begins
P.P.G. Sugathadasa -Thihagoda group cor
Construction work on the first phase of the proposed
Matara-Kataragama new rail-road from Matara to Beliatta will be
inaugurated tomorrow at 3 p.m. at Beliatta.
According to Director attached to Matara-Kataragama New Rail-Road
Construction Project V. Amaratunga, it is expected to be completed by
2015. New railway stations are to be constructed at Kekanadura,
Babarenda, Wavurukannala and Beliatta and sub stations too would be
erected at Piladuwa and Weherahena.
The Sri Lanka's longest railway tunnel which will be of over 600
meters in length will also be constructed at Kekanadura on this rail-way
extension line he said.
The estimated cost of the first phase of the Matara-Kataragama
railway from Matara to Beliatte is Dollars 272 million. People's
Republic of China is funding the Project Director V. Amaratunga said.
|