'Dam renovation ahead of schedule'
By Gamini Warushamana
The Dam Safety and Water Resources Planning Project (DSWRPP) has
achieved 86.38 percent progress in fund disbursement and 72 percent
physical progress, a year ahead of schedule, said Project Director D.C.S.
Elakanda.
 |
Renovated dam of the
Kandalama tank |
He said that it was a significant achievement in respect of foreign
funded projects.
World Bank Vice President for the South Asian region, Philippe Le
Houerou, during his recent visit to Sri Lanka, lauded the DSWRPP
achievement.
He inspected the Kantale dam, which collapsed in 1986 causing major
destruction and was happy with the improved dam safety measures after
renovation. The DSWRPP is funded by the World Bank and it provided a Rs.
7,545 million interest free credit facility for phase one of the
project, while the Government provided Rs. 642 million, he said.
"Under phase one, 32 major reservoirs were selected and initially the
project was due to be completed by 2013. However, the implementation of
the sub projects was behind schedule because engineering works were
complicated due to several reasons.
To renovate these dams water in the reservoirs had to be discharged
and these decisions were associated with huge socio-economic costs. For
instance the livelihood of the farmer community and fishers, drinking
water supply to towns or electricity generation were affected and we had
to introduce various measures to minimise socio-economic costs.
Therefore, the Ministry of Irrigation and Water Resource Planning
sought extension of project duration by two years.
Accordingly, the project was rescheduled to be completed by June
2015.
We carried out the work efficiently to achieve the target and are
happy with the progress and are confident that we will complete the
project on schedule," Elakanda said.
He said that the project has already averted several possible
catastrophes caused by the impact of climate change. There was a
possibility of a catastrophe during the 2011 flood in several large
reservoirs such as Ridiyagama, Tabbowa and Usgala Siyambalangamuwa that
were vulnerable due to weak and dilapidated dams.
These dams had been identified as high-risk dams and renovation work
was accelerated after scientific studies on the stability of the dam and
spill and sluice gates were made.
As some of these reservoirs now receive water from the Mahaweli
system their dams had to be strengthened. Renovation work includes
strengthening the dam and improving operational efficiency of the spill
and sluice gates.
The World Bank has also recognised the livelihood support mechanism
used by the DSWRPP as a model to be replicated in similar projects
funded by the bank worldwide.
This mechanism was used to support communities that were affected due
to the renovation of Tabbowa, Ridegama and Usgala Siyabalangamuwa.
Additional funding for renovation of another 30 dams have been
received, due to these achievements. The same methodology will be used
in the renovation of these dams.
He said that in these 30 sub projects, several large tanks in the
Northern province have also been included in the second phase and
Pandivirichchan and Muthu Iyan Kaddu tanks in the Mulathivu, Koorai tank
in the Mannar district are among them.
These tanks were neglected for several decades due to terrorism and
essential renovation hadn't been done.
According to Elakanda, as a result of these achievements in the
renovation of dams, the World Bank and the government have given more
responsibilities to the DSWRPP.
The renovation work of two tanks of the Kandy water supply scheme
under the Strategic Cities Project have also been given to the DSWRPP
and additional funds amounting to Rs. 83 million were allocated.
The government now considers dam safety as a continuous process and
not a one-off project. Therefore, the sustainability of the project
should be ensured by continuous maintenance.
For this purpose, the DSWRPP has initiated a human resource
development program for partner organisations.
"We obtained foreign consultancy at a cost for this project and we
hope to train our own experts to continue operations. Accordingly, two
training institutes will be developed. The training institute of the
Irrigation Department in Galgamuwa will be developed at a cost of Rs.
200 million.
Rs. 450 million will be spent to upgrade the technical officers
training institute of the Mahaweli Authority in Kotmale to international
level," Elakanda said.
He said that the shortage of human resources, especially engineers
and technical officers is a huge issue in keeping up this widespread
irrigation network.
"We have funds for the development of the irrigation network in the
country but there is a lack of human resource," he said.
Departments and institutions involved in water resource management
such as the Irrigation Department, Mahaweli Authority, Water Supply and
Drainage Board and the Ceylon Electricity Board (CEB) are now partners
of the DSWRPP with the implementation of the DSWRPP multi-sector water
resources planning and management system. The project has invested on
capacity building of these institutions.
 |
The Tabbowa tank spill
gates under renovation |
Under the DSWRPP, 122 hydrometric stations have been set up
islandwide to monitor rainfall, water level and water flow to
reservoirs. These centres collect several sets of data regularly and
send them to the Department of Irrigation and the Mahaweli Authority via
satellite.
This data will help avert a catastrophe in heavy rain and flood
situations. Data is collected manually at present. In the future, water
levels in the whole network of reservoirs will be monitored from a
single centre.
Since the cost of obtaining this data is borne by public funds, the
DSWRPP will make maximum use of it and share the data with research
institutes and universities.
"A German company has set up the hydrometric stations and the
training of local staff is also under way.
The project also includes the renovation of two tunnels, Polgolla and
New Laxapana owned by the CEB. Since this tunnel renovation is a complex
process we obtained foreign consultancy. It was difficult to get the
consent to shut down the tunnels due to the huge socio-economic costs.
The renovation brought massive gains to the CEB as there was a huge
water leak, estimated at 230 litres per second. The estimated loss to
this leak was Rs. 120 million per year.
The investment on the New Laxapana tunnel renovation is Rs.100
million and it could be covered within a year. The renovation work of
the tunnel is now under way.
The shut down of the Polgolla tunnel will cause a water cut in Matale
town and we have to find an alternative solution before the tunnel is
shut down," he said. |