Always breaking down! Always breaking down!
Frequently out of commission due to numerous
technical faults, the Norochcholai coal power plant is not likely to be
decommissioned despite allegations of sub standard parts and speculation
about its future viability:
by Rukshana Rizwie
 |
Courtesy:
colombologistics |
The Lakvijaya Power Station also known as the Norocholai Coal Power
Plant was shut down on nearly 30 occasions since it was commissioned in
2011, Chairman, Ceylon Electricity Board Anura Senaka Wijayapala told
the Sunday Observer.
"Most of the time the breakdowns were due to technical faults in the
auxiliary equipment brought down from China," he said. "However we
experienced these issues only in Phase I of the project, which as we all
know was an accelerated program in 2011."
Ananda Nimalarathna, a retired Ceylon Electricity Board (CEB) trade
union convenor endorsed the fact that most of the time the breakdown was
due to technical failure. Despite the absence of any assurance that it
would not falter again, experts say the plant will not be
decommissioned, since it is the only plant which can provide half of Sri
Lanka's energy needs at present.
"The concept and functioning of a coal power plant is still new to
everyone," he said stressing that the failure of the plant to get off
the ground is quoted by populist politicians to score political brownie
points. "No one talks about how many times the Victoria or Laxapana
shuts down and never will."
"However, there is no way this plant would be decommissioned," a
Ceylon Electricity Board(CEB) engineer who oversees the plant told the
Sunday Observer. "The power plant provides 45% of the nation's energy
requirements. In January this year alone, the plant added 900 megawatts
(MW) of electricity to the national grid,"he said.
Contribution
It is envisioned that the plant will produce 5,300 million watts this
year to increase its contribution to the national grid to 50 percent.
According to the National Energy Sector Development plan released by
the Ministry of Power and Energy, Sri Lanka's total energy requirement
was around 11,125 Kilotonne of oil equivalent (ktoe) in 2013, and the
primary energy supply mainly consisted of 4,814 (ktoe) of biomass, 4,582
ktoe of fossil fuels, and 1,442 ktoe of hydro. Today a kilotonne is
equivalent to 99.93 tonnes of oil.
Meanwhile, the installed power generation capacity is approximately
4,050 MW, consisting of 900 MW of coal power, 1,335 MW of oil burning
thermal power, 1,375 MW of hydro power and 442 MW of non-conventional
renewable energy sources such as wind, mini hydro, biomass and solar
power plants.
"To everyone who says that substandard equipment was brought to build
this plant, we ask them to show CEB engineers who worked on this project
credible evidence that this is really so" he said. "I was present when
the documents for the project were reviewed and when the payments were
discussed.
There were instances when we defaulted payments but in no uncertain
terms did we intentionally bring down sub-standard equipment for this
plant," he said.
When asked about the veracity of reports that equipment showed
visible signs of corrosion, he said, "When construction began at the
plant, signs of corrosion had already begun as far back as 2006.
Stainless steel may not corrode in Colombo but it does, when half of it
is immersed in water at the edge of a peninsula. It's not rocket science
to understand that. We were expecting that but we also know that it can
be repaired."
Nimalaratne, however said that there were concerns regarding the
project being brought up by various politicians from time to time.
"There was concern whether the Chinese who undertook this project
deceived us," he said. "There were rumours of substandard machines being
used at the plant, and low quality coal being imported for the project.
While these rumours haven't been substantiated, persistent breakdowns
only seem to give credibility to these claims."
Learning curve
Engineers who are presently working at the Norochcholai plant added
that when the plant was first commissioned, they knew it would be a
learning curve. "Nothing of this magnitude has been attempted before in
the country and unlike wind or thermal power plants, a coal-powered
plant falters often, we knew it would take us time to learn the
process," an engineer said. He said the China Machinery Engineering
Corporation which was contracted to build the plant assisted in times of
crisis. Authoritative sources at the Ministry of Power and Energy told
the Sunday Observer that despite announcements from higher authorities
in the Ministry about the controversial plant, there is no evidence to
prove that the plant was built below international standards.
Deputy Minister of Power and Energy, Ajith P. Perera, made damning
revelations this past week citing that the plant had been built with
substandard and outdated material. "At the time the technology of the
brands agreed were outdated, and was not suitable for a plant in Sri
Lanka, for which the government had agreed," he said.
He added that authorities were unable to file legal action demanding
compensation since the agreement was signed during the previous regime.
Serious technical faults
The Minister said if a lightning strike could cause a plant to stall,
the inference is that there are serious technical faults which may have
been overlooked.
Last month, the Norochcholai power plant experienced a breakdown
following a sudden islandwide power outage, disrupting power supply
throughout the country.
The Norochcholai Power Plant according to its engineers takes three
days to kick start once the entire plant shuts down.
This also made the CEB to request the public to use electricity
sparingly until all plants were fully operational. |